A. once through project
B. maintenance jobs
C. research and development
D. all non-technical jobs
E. all of the above
Production Technology
Production Technology
A. synthesising in concepts
B. is built of activities oriented program-mes
C. is, based on one time eytimate
D. is used for repetitive works
E. all of the above
A. establishes the relative priorities among various activities on a common basis
B. determines the status of each activity
C. adjusts automatically changes in activity progress
D. is a dynamic system
E. none of the above
A. normal time
B. slow time
C. crash time
D. standard time
E. none of the above
A. to concentrate his attention on critical activities
B. to divert the resources from non-critical advanced activities to critical activities
C. to be cautious for avoiding any delay in the critical activities to avoid delay of the whole project
D. all of the above
E. none of the above
A. duration
B. total float
C. free float
D. interfering float
E. none of the above
A. latest start time – earliest start time
B. latest finish time – earliest finish time (EFT)
C. TL-EFT
D. all of the above
E. none of the above
A. normal
B. binomial
C. beta
D. exponential
E. Gaussian
A. EF=ES+D
B. LS=LF-D
C. LF = LS + D
D. D = EF-ES
E. all of the above
A. event
B. free float
C. artificial
D. constraint
E. dummy