A. duration
B. total float
C. free float
D. interfering float
E. none of the above
Related Mcqs:
- The artificial activity; which indicates that an activity following it cannot be started unless, the preceding activity is complete, is known as_________________?
A. event
B. free float
C. artificial
D. constraint
E. dummy - If E is the duration, ES and EF are die earliest start and finish times, LS and LF are latest start and finish times, then the following relation holds good______________________?
A. EF=ES+D
B. LS=LF-D
C. LF = LS + D
D. D = EF-ES
E. all of the above - The time required to complete a job is established and a bonus is paid to the worker based on the exact % of time saved. This type of incentive plan is known as_________________?
A. Dry work Plan
B. Halsey Premium Plan
C. Taylor Plan
D. Bedaux Plan
E. Rowan Plan - The time required to complete a task is established and a bonus is paid to the worker for every hour he saves from the established time required. This type of incentive plan is known as_________________?
A. Rowan Plan
B. Bedaux Plan
C. Taylor Differential Piece rate system
D. Halsey Premium plan
E. Day work plan - The difference between the time available to do the job and the time required to do the job, is known as_________________?
A. event
B. float
C. duration
D. constraint
E. none of the above - The probability distribution of project completion in PERT follows following distribution_________________?
A. normal
B. binomial
C. beta
D. exponential
E. Gaussian - The time which results in the least possible direct cost of an activity is known as________________?
A. normal time
B. slow time
C. crash time
D. standard time
E. none of the above - The grouping of activities into organisational units is called_________________?
A. corporate plans
B. higher level management
C. functional authority
D. departmentatidn
E. company policy - Critical path moves along the activities having total float of_____________________?
A. positive value
B. negative value
C. zero value
D. same value
E. none of the above - The critical activity has____________________?
A. maximum float
B. minimum float
C. zero float,
D. average float
E. none of these