A. normal time
B. slow time
C. crash time
D. standard time
E. none of the above
Related Mcqs:
- The artificial activity; which indicates that an activity following it cannot be started unless, the preceding activity is complete, is known as_________________?
A. event
B. free float
C. artificial
D. constraint
E. dummy - Frederick W. Taylor introduced a system of working known as________________?
A. line organisation
B. line and staff organisation
C. functional organisation
D. effective organisation
E. none of the above - The time by which the activity completion time can be delayed without affecting the start of succeeding activities, is Known as_________________?
A. duration
B. total float
C. free float
D. interfering float
E. none of the above - The time of completing a project in network analysis is given by following time of the critical activity meeting at the finalitiode_________________?
A. early finish
B. early start
C. late start
D. late finish
E. none of the above - The probability distribution of activity times in PERT follows following distribution__________________?
A. normal
B. binomial
C. beta
D. exponential
E. Gaussian - If TL is the largest allowable event occurrence time, total activity slack (s) is equal to__________________?
A. latest start time – earliest start time
B. latest finish time – earliest finish time (EFT)
C. TL-EFT
D. all of the above
E. none of the above - Pick up the correct statement. Dummy activity on a PERT/CPM chart means, it_________________?
A. consumes time, but no resources
B. consumes resources but no time
C. consumes neither time nor resources
D. is a dangling event
E. consumes both resources and time - Activity s,lack or float of any event on a PERT/CPM chart is represented by__________________?
A. latest start time of succeeding event -earliest finish time of preceding event activity time
B. latest start time of the event – earliest start time of the event
C. latest finish time of event – earliest finish time of the event
D. anyone of the above
E. none of the above - The critical activity has____________________?
A. maximum float
B. minimum float
C. zero float,
D. average float
E. none of these - Works cost implies________________?
A. primary cost
B. factory cost
C. factory expenses
D. primary cost + factory expenses
E. none of the above