A. early finish
B. early start
C. late start
D. late finish
E. none of the above
Related Mcqs:
- The artificial activity; which indicates that an activity following it cannot be started unless, the preceding activity is complete, is known as_________________?
A. event
B. free float
C. artificial
D. constraint
E. dummy - The critical path of a network represents_______________________?
A. the minimum time required for completion of project
B. the maximum time required for completion of project
C. maximum cost required for completion of project
D. minimum cost required for completion of project
E. none of the above - The critical activity has____________________?
A. maximum float
B. minimum float
C. zero float,
D. average float
E. none of these - In PERT analysis, critical path is obtained by joining events having___________________?
A. +ve slack
B. -ve slack
C. zero sldck
D. dummy activities
E. critical activities - Pick up the incorrect statement from the following. A critical ratio scheduling____________________?
A. establishes the relative priorities among various activities on a common basis
B. determines the status of each activity
C. adjusts automatically changes in activity progress
D. is a dynamic system
E. none of the above - An event is indicated on the network by_________________?
A. a straight line
B. a number enclosed in a circle or a square
C. a straight line with circles at the ends
D. a dotted line
E. an arrow - Critical Path Net Work helps an engineer_________________?
A. to concentrate his attention on critical activities
B. to divert the resources from non-critical advanced activities to critical activities
C. to be cautious for avoiding any delay in the critical activities to avoid delay of the whole project
D. all of the above
E. none of the above - Slack of various events on the critical path in PERT/CPM chart___________________?
A. increases continuously
B. decreases continuously
C. remains constant
D. may increase or decrease depending on various factors
E. unpredictable - Critical path moves along the activities having total float of_____________________?
A. positive value
B. negative value
C. zero value
D. same value
E. none of the above - The probability distribution of activity times in PERT follows following distribution__________________?
A. normal
B. binomial
C. beta
D. exponential
E. Gaussian