A. establishes the relative priorities among various activities on a common basis
B. determines the status of each activity
C. adjusts automatically changes in activity progress
D. is a dynamic system
E. none of the above
Related Mcqs:
- Pick up the incorrect statement from the following?
A. an activity of the project is denoted by an arrow on the net work
B. the tail of the arrow indicates the start of the activity
C. the head of the arrow indicates the end of,the activity!
D. the arrows are drawn (to scale from) left to right
E. each activity consumes a given time - Pick up the incorrect statement about advantages of work sampling_________________?
A. permits a fine breakdown of activities and delays
B. simultaneous study of many operators may be made by a single observer
C. calculations are easier, method is economical and less time consuming
D. no time measuring devices are generally needed
E. as operators are not watched for long periods, chances of obtaining misleading results are less - Pick up the correct statement from the following?
A. critical path method is an improvement upon bar chart method
B. critical path method provides a realistic approach to the daily problems
C. critical path method avoids delays which are very common in bar chart
D. critical path method was invented by Morgan R. Walker of Dupot and James E. Kelley of Remington U.S.A in 1957
E. all of the above - Pick up the correct statement from the following?
A. the float may be positive, zero or negative
B. if the float is positive and the activity is delayed by a period equal to its total float, the completion of project in not delayed
C. if the float of an activity is negative, delay in its performance is bound to delay the completion of project
D. if the float of an activity is zero, the activity is critical and any delay in its performance will delay the whole project
E. all of the above - Pick up the correct statement from the following?
A. programmer evaluation and review technique is event oriented
B. programmer evaluation and review technique is not event oriented
C. critical path method is event oriented
D. critical.path method is not activity oriented
E. none of the above - Pick up the correct statement. Dummy activity on a PERT/CPM chart means, it_________________?
A. consumes time, but no resources
B. consumes resources but no time
C. consumes neither time nor resources
D. is a dangling event
E. consumes both resources and time - Pick up the correct statement about relationship between various floats______________________?
A. free float = total float
B. independent float = total float
C. independent float > free float
D. free float > total float
E. independent float < free float - The time of completing a project in network analysis is given by following time of the critical activity meeting at the finalitiode_________________?
A. early finish
B. early start
C. late start
D. late finish
E. none of the above - Critical Path Net Work helps an engineer_________________?
A. to concentrate his attention on critical activities
B. to divert the resources from non-critical advanced activities to critical activities
C. to be cautious for avoiding any delay in the critical activities to avoid delay of the whole project
D. all of the above
E. none of the above - Slack of various events on the critical path in PERT/CPM chart___________________?
A. increases continuously
B. decreases continuously
C. remains constant
D. may increase or decrease depending on various factors
E. unpredictable