A. latest start time – earliest start time
B. latest finish time – earliest finish time (EFT)
C. TL-EFT
D. all of the above
E. none of the above
Related Mcqs:
- The artificial activity; which indicates that an activity following it cannot be started unless, the preceding activity is complete, is known as_________________?
A. event
B. free float
C. artificial
D. constraint
E. dummy - Slack represents the difference between the___________________?
A. latest allowable time and the normal expected time
B. latest allowable time and the earliest expected time
C. proposed allowable time and the earliest expected time
D. normal allowable time and the latest expected time
E. project initiation tune and actual starting time - Slack of various events on the critical path in PERT/CPM chart___________________?
A. increases continuously
B. decreases continuously
C. remains constant
D. may increase or decrease depending on various factors
E. unpredictable - Positive slack on a PERT indicates that project is________________?
A. ahead of schedule
B. beyond schedule
C. as per schedule
D. on critical path
E. none of the above - Activity s,lack or float of any event on a PERT/CPM chart is represented by__________________?
A. latest start time of succeeding event -earliest finish time of preceding event activity time
B. latest start time of the event – earliest start time of the event
C. latest finish time of event – earliest finish time of the event
D. anyone of the above
E. none of the above - Standing orders which are statutory are applicable to__________________?
A. all industries
B. all process industries and thermal power plants
C. only major industries
D. only key industries
E. all industries employing more than 100 workers - In A-B-C control policy, maximum attention is given to__________________?
A. those items which consume money
B. those items which are not readily available
C. those x items which are in more demand
D. those items which consume more money
E. proper quality assurance program-mes - An event is indicated on the network by_________________?
A. a straight line
B. a number enclosed in a circle or a square
C. a straight line with circles at the ends
D. a dotted line
E. an arrow - The probability distribution of activity times in PERT follows following distribution__________________?
A. normal
B. binomial
C. beta
D. exponential
E. Gaussian - The time by which the activity completion time can be delayed without affecting the start of succeeding activities, is Known as_________________?
A. duration
B. total float
C. free float
D. interfering float
E. none of the above