A. ahead of schedule
B. beyond schedule
C. as per schedule
D. on critical path
E. none of the above
Related Mcqs:
- Slack of various events on the critical path in PERT/CPM chart___________________?
A. increases continuously
B. decreases continuously
C. remains constant
D. may increase or decrease depending on various factors
E. unpredictable - The probability distribution of project completion in PERT follows following distribution_________________?
A. normal
B. binomial
C. beta
D. exponential
E. Gaussian - PERT stands for k (fit) project evaluation and review technique__________________?
A. project examination and review technique
B. project evaluation and reporting technique
C. process execution and reporting technology
D. project execution and results technique - Slack represents the difference between the___________________?
A. latest allowable time and the normal expected time
B. latest allowable time and the earliest expected time
C. proposed allowable time and the earliest expected time
D. normal allowable time and the latest expected time
E. project initiation tune and actual starting time - If TL is the largest allowable event occurrence time, total activity slack (s) is equal to__________________?
A. latest start time – earliest start time
B. latest finish time – earliest finish time (EFT)
C. TL-EFT
D. all of the above
E. none of the above - The basic difference between PERT and CPM is that_____________?
A. PERT deals with events and CPM with activities
B. critical path is determined in PERT only
C. costs are considered on CPM only and not in PERT
D. guessed times are used in PERT and evaluated times in CPM
E. PERT is used in workshops and CPM in plants - The probability distribution of activity times in PERT follows following distribution__________________?
A. normal
B. binomial
C. beta
D. exponential
E. Gaussian - Activity s,lack or float of any event on a PERT/CPM chart is represented by__________________?
A. latest start time of succeeding event -earliest finish time of preceding event activity time
B. latest start time of the event – earliest start time of the event
C. latest finish time of event – earliest finish time of the event
D. anyone of the above
E. none of the above - Criticalpath on PERT/CPM chart is obtained by joining the events having____________________?
A. maximum slack
B. minimum slack
C. average slack
D. no slack
E. judgement and experience - PERT and CPM are__________________?
A. techniques to determine project status
B. decision making techniques
C. charts which increase aesthetic appearance of rooms
D. aids to determine cost implications of project
E. aids to the decision maker