A. EF=ES+D
B. LS=LF-D
C. LF = LS + D
D. D = EF-ES
E. all of the above
Related Mcqs:
- The time by which the activity completion time can be delayed without affecting the start of succeeding activities, is Known as_________________?
A. duration
B. total float
C. free float
D. interfering float
E. none of the above - The probability distribution of activity times in PERT follows following distribution__________________?
A. normal
B. binomial
C. beta
D. exponential
E. Gaussian - Basic motion time study gives times for basic motions in ten thousandths of_______________?
A. second
B. minute
C. hour
D. day
E. none of the above - Micromotion study involves following number of fundamental hand motions_______________?
A. 8
B. 12
C. 16
D. 20
E. 24 - Which of the following organisations is best suited for steel plants__________________?
A. functional organisation
B. line organisation
C. staff organisation
D. line, staff and functional organisations
E. scalar organisation - Which of the following layouts is suited to job production__________________?
A. process layout
B. product layout
C. fixed position layout
D. plant layout
E. functional layout - Which of the following plans motivates supervisors by paying a premium on time saved by workers_________________?
A. Halsey plan
B. Rowan plan
C. Haynes plan
D. Emerson’s plan
E. Taylor’s plan - For ship vessel industry the following layout is best suited_________________?
A. process layout
B. product layout
C. fixed position layout
D. plant layout
E. functional layout - The probability distribution of project completion in PERT follows following distribution_________________?
A. normal
B. binomial
C. beta
D. exponential
E. Gaussian - Which of the following depreciation system ensures that the interest be charged on the cost of machine asset every year on the book value, but the rate of depreciation every year remains constant_____________________?
A. sinking fund method
B. straight line method
C. A-B-C charging method
D. annuity charging method
E. diminishing balance method