A. normal time + allowances
B. normal time + idle time + allowances
C. normal time + idle time
D. only normal time for an operation
E. none of the above
Related Mcqs:
- Standard time as compared to normal time is_______________?
A. greater
B. smaller
C. equal
D. there is no such correlation
E. none of the above - The standard time for a job is_________________?
A. total work content
B. base time + relaxation time
C. total work content + basic time
D. total work content + delay contingency allowance
E. total work content + relaxation time - The allowed time for a job equals standard time plus___________________?
A. policy allowance
B. interference allowance
C. process allowance
D. learning allowance
E. unforeseen allowance - According to Rowan plan, if H = hourly rate, A = actual time and S = standard time, then wages will be___________________?
A. HA
B. HA + (S~A) HA
C. HA + ^^-H
D. HA + ^^-H
E. HA + ^^-HA - ‘Value’ for value engineering and analysis purposes is defined as_____________________?
A. purchase value
B. saleable value
C. depreciated value
D. present worth
E. function/cost - Break-even analysis can be used for__________________?
A. short run analysis
B. long run analysis
C. average of above two run analysis
D. there is no such criterion
E. none of the above - The most popular type of organisation used for Civil Engineering Constructions is_________________?
A. line organisation
B. line and staff organisation
C. functional organisation
D. effective organisation
E. none of the above - Which of the following equations is not in conformity with others______________?
A. organisation performance x motivation = profits
B. knowledge x skill = ability
C. ability x motivation = performance
D. attitude x situation = motivation
E. performance x resources - The assumption in PERT is__________________?
A. a project will always be behind schedule, if left uncorrected
B. cost of project will always be more than the estimated cost, if no timely corrections are taken
C. a project can be subdivided into a set of predictable, independent activities
D. activities are fixed and can’t be changed ,
E. commissioning time can be changed, if activities are behind schedule - The linear programming techniques can be applied successfully to industries like_________________?
A. iron and steel
B. food processing
C. oil and chemical
D. banking
E. all of the above