A. purchase value
B. saleable value
C. depreciated value
D. present worth
E. function/cost
Related Mcqs:
- The term ‘value’ in value engineering refers to_______________?
A. total cost of the product
B. selling price of the product
C. utility of the product
D. manufactured cost of the product
E. depreciation value - Value engineering aims at finding out the________________?
A. depreciation value of a product
B. resale value of a product
C. major function of the item and accomplishing the same at least cost without change in quality
D. break even point when machine re-quires change
E. selling price of an item - The technique of value analysis can be applied to____________________?
A. complicated items only
B. simple items only
C. crash programmer items only
D. cost consciousness items only
E. any item - Father of industrial engineering is_________________?
A. Jeck Gilberth
B. Gnatt
C. Taylor
D. Newton
E. none of the above - The most popular type of organisation used for Civil Engineering Constructions is_________________?
A. line organisation
B. line and staff organisation
C. functional organisation
D. effective organisation
E. none of the above - Standard time is defined as ____________________?
A. normal time + allowances
B. normal time + idle time + allowances
C. normal time + idle time
D. only normal time for an operation
E. none of the above - ABC analysis deals with_________________?
A. analysis of process chart
B. flow of material
C. ordering schedule of job
D. controlling inventory costs money
E. all of the above - Break-even analysis can be used for__________________?
A. short run analysis
B. long run analysis
C. average of above two run analysis
D. there is no such criterion
E. none of the above - The time of completing a project in network analysis is given by following time of the critical activity meeting at the finalitiode_________________?
A. early finish
B. early start
C. late start
D. late finish
E. none of the above - In PERT analysis, critical path is obtained by joining events having___________________?
A. +ve slack
B. -ve slack
C. zero sldck
D. dummy activities
E. critical activities