A. short run analysis
B. long run analysis
C. average of above two run analysis
D. there is no such criterion
E. none of the above
Related Mcqs:
- TMU in method time measurement stands for__________________?
A. time motion unit
B. time measurement unit
C. time movement unit
D. technique measurement unit
E. time method unit - The simplex method is the basic method for__________________?
A. value analysis
B. operation research
C. linear programming
D. model analysis
E. none of the above - ABC analysis deals with_________________?
A. analysis of process chart
B. flow of material
C. ordering schedule of job
D. controlling inventory costs money
E. all of the above - ‘Value’ for value engineering and analysis purposes is defined as_____________________?
A. purchase value
B. saleable value
C. depreciated value
D. present worth
E. function/cost - Motion study involves analysis of________________?
A. actions of operator
B. layout of work place
C. tooling and equipment
D. all of the above
E. none of the above - The technique of value analysis can be applied to____________________?
A. complicated items only
B. simple items only
C. crash programmer items only
D. cost consciousness items only
E. any item - The time of completing a project in network analysis is given by following time of the critical activity meeting at the finalitiode_________________?
A. early finish
B. early start
C. late start
D. late finish
E. none of the above - In PERT analysis, critical path is obtained by joining events having___________________?
A. +ve slack
B. -ve slack
C. zero sldck
D. dummy activities
E. critical activities - PERT analysis is based on____________________?
A. optimistic time
B. pessimistic time
C. most likely time
D. all of the above
E. none of the above - Military organisation is known as_______________________?
A. line organisation
B. line and staff organisation
C. functional organisation
D. all of the above
E. none of the above