A. 10
B. 9
C. 11
D. 12
Work done by P in 1 day = 1/24
Work done by Q in 1 day = 1/9
Work done by R in 1 day = 1/12
Work done by Q and R in 1 day = 1/9 + 1/12 = 7/36
Work done by Q and R in 3 days = 3×7/36 = 7/12
Remaining work = 1 – 7/12 = 5/12
Number of days in which P can finish the remaining work = (5/12) / (1/24) = 10
Advertisement
Related Mcqs:
- A,B,C, can do a work in 8,14,16 days respectively. A does the work for the first 2 days. B continues from it and finishes 2/3rd of the remaining work. C finishes the remaining work. How many days would have taken to complete the work?
- A. 13 B. 11 C. 12 D. 15...
- A and B can complete a work in 15 days and 10 days respectively. They started doing the work together but after 2 days B had to leave and A alone completed the remaining work. The whole work was completed in___________?
- A. 8 days B. 10 days C. 12 days D. 15 days...
- A and B can finish a work 30 days if they work together. They worked together for 20 days and then B left. A finished the remaining work in another 20 days. In how many days A alone can finish the work?
- A. 70 B. 50 C. 40 D. 60...
- A and B can do a piece of work in 21 and 24 days respectively.They start the work together and after some days, A leaves and B completes the rest of the task in 9 days. After how many days did A leave?
- A. 5 B. 6 C. 7 D. 8...
- P and Q can do a work in 30 days. Q and R can do the same work in 24 days and R and P in 20 days. They started the work together, but Q and R left after 10 days. How many days more will P take to finish the work?
- A. 10 B. 8 C. 18 D. 19...
- P can finish a work in 18 days. Q can finish the same work in 15 days. Q worked for 10 days and left the job. how many days does P alone need to finish the remaining work?
- A. 8 B. 6 C. 4 D. 2...
- P and Q can complete a work in 15 days and 10 days respectively. They started the work together and then Q left after 2 days. P alone completed the remaining work. The work was finished in__________days.
- A. 12 B. 15 C. 22 D. 20...
- Twelve children take sixteen days to complete a work which can be completed by 8 adults in 12 days. After working for 3 days, sixteen adults left and six adults and four children joined them. How many days will they take to complete the remaining work ?
- A. 3 days B. 4 days C. 6 days D. 8 days Submitted by: মোঃ আশাদুজ্জামান...
- C takes 6 days to complete half of a work and D takes 5 days to complete 1/3rd of the same work. They take turns to complete the task. If C works for the first 4 days, in how many days will D complete the rest of the work without the help of C?
- A. 10 days B. 12 days C. 8 days D. 9 days...
- P is able to do a piece of work in 15 days and Q can do the same work in 20 days. If they can work together for 4 days, what is the fraction of work left?
- A. 8/15 B. 7/15 C. 11/15 D. 2/11...
Advertisement