A. 70
B. 50
C. 40
D. 60
Amount of work done by A and B in 1 day = 1/30
Amount of work done by A and B in 20 days = 20 × (1/30) = 20/30 = 2/3
Remaining work – 1 – 2/3 = 1/3
A completes 1/3 work in 20 days
Amount of work A can do in 1 day = (1/3)/20 = 1/60
=> A can complete the work in 60 days
Related Mcqs:
- P can finish a work in 18 days. Q can finish the same work in 15 days. Q worked for 10 days and left the job. how many days does P alone need to finish the remaining work?
A. 8
B. 6
C. 4
D. 2 - A alone can finish a work in X days. B alone can finish the same work in X+5 days. Together, they take 6 days to complete the work. Find X
A. 12
B. 8
C. 10
D. 9 - P and Q can complete a work in 15 days and 10 days respectively. They started the work together and then Q left after 2 days. P alone completed the remaining work. The work was finished in__________days.
A. 12
B. 15
C. 22
D. 20 - A alone can finish a work in 10 days and B alone can do it in 15 days. If they work together and finish, then out of a total wages of Rs.75. A will get:___________?
A. 35 Rs.
B. 40 Rs.
C. 45 Rs.
D. None of these - A and B can finish a piece of work in 20 days .B and C in 30 days and C and A in 40 days. In how many days will A alone finish the job?
A. 48
B. 34(2/7)
C. 44
D. 45 - A,B,C, can do a work in 8,14,16 days respectively. A does the work for the first 2 days. B continues from it and finishes 2/3rd of the remaining work. C finishes the remaining work. How many days would have taken to complete the work?
A. 13
B. 11
C. 12
D. 15 - P and Q can do a work in 30 days. Q and R can do the same work in 24 days and R and P in 20 days. They started the work together, but Q and R left after 10 days. How many days more will P take to finish the work?
A. 10
B. 8
C. 18
D. 19 - P takes twice as much time as Q or thrice as much time as R to finish a piece of work. They can finish the work in 2 days if work together. How much time will Q take to do the work alone?
A. 7
B. 8
C. 9
D. 6
Let P takes x days to complete the work
Then Q takes x/2 days and R takes x/3 days to finish the work
Amount of work P does in 1 day = 1/x
Amount of work Q does in 1 day = 2/x
Amount of work R does in 1 day = 3/x
Amount of work P,Q and R do in 1 day = 1/x + 2/x + 3/x = 1/x (1 + 2 + 3) = 6/x
6/x = 2
=> x = 12
=> Q takes 12/2 days = 6 days to complete the work - A completes 80% of a work in 20 days. Then B also joins and A and B together finish the remaining work in 3 days. How long does it need for B if he alone completes the work?
A. 37 ½ days
B. 22 days
C. 31 days
D. 22 days - A and B can complete a work in 15 days and 10 days respectively. They started doing the work together but after 2 days B had to leave and A alone completed the remaining work. The whole work was completed in___________?
A. 8 days
B. 10 days
C. 12 days
D. 15 days