A. 8 days
B. 10 days
C. 12 days
D. 15 days
(A.+ B)’s 1 day’s work = ( 1/15 + 1/10 ) = 1/6 Work done by A and B in 2 days = ( 1/6 X 2 ) = 1/3 Remaining work = ( 1 – 1/6 ) = 2/3
Now, 1/15 work is done by A in 1 day. so 2/3 work will be done by A in ( 15 X 2/3 ) = 10 days Hence, total time taken = (10 + 2) = 12 days.
Advertisement
Related Mcqs:
- P and Q can complete a work in 15 days and 10 days respectively. They started the work together and then Q left after 2 days. P alone completed the remaining work. The work was finished in__________days.
A. 12
B. 15
C. 22
D. 20 - A,B,C, can do a work in 8,14,16 days respectively. A does the work for the first 2 days. B continues from it and finishes 2/3rd of the remaining work. C finishes the remaining work. How many days would have taken to complete the work?
A. 13
B. 11
C. 12
D. 15 - 4 men and 2 woman can complete a work in 2 days. If 2 men alone take 5 days to complete the work, find the time taken by 2 women alone to complete the work.
A. 15 days
B. 10 days
C. 8 days
D. 20 days - P and Q can complete a work in 20 days and 12 days respectively. P alone started the work and Q joined him after 4 days till the completion of the work. How long did the work last?
A. 5 days
B. 10 days
C. 15 days
D. 12 days - C takes 6 days to complete half of a work and D takes 5 days to complete 1/3rd of the same work. They take turns to complete the task. If C works for the first 4 days, in how many days will D complete the rest of the work without the help of C?
A. 10 days
B. 12 days
C. 8 days
D. 9 days - P can do a work in the same time in which Q and R together can do it. If P and Q work together, the work can be completed in 10 days. R alone needs 50 days to complete the same work. then Q alone can do it in__________?
A. 30 days
B. 25 days
C. 20 days
D. 15 days - Twelve children take sixteen days to complete a work which can be completed by 8 adults in 12 days. After working for 3 days, sixteen adults left and six adults and four children joined them. How many days will they take to complete the remaining work ?
A. 3 days
B. 4 days
C. 6 days
D. 8 daysSubmitted by: মোঃ আশাদুজ্জামান
- A and B together can complete a work in 1.2 days,. A alone can complete it in 20 days. If B does the work only for half a day daily, then in how many days A and B together will complete the work ?
A. 10 days
B. 11 days
C. 15 days
D. 20 days - A and B can finish a work 30 days if they work together. They worked together for 20 days and then B left. A finished the remaining work in another 20 days. In how many days A alone can finish the work?
A. 70
B. 50
C. 40
D. 60 - P can do a work in 24 days. Q can do the same work in 9 days and R can do the same in 12 days. Q and R start the work and leave after 3 days. P finishes the remaining work in_________days.
A. 10
B. 9
C. 11
D. 12
Advertisement