A. 12
B. 8
C. 10
D. 9
Part of work completed by A in a day = 1/X Part of work completed by B in a day
= 1/(X+5) (1/X)+(1/(X+5)) = 1/6 (2X+5)/(X²+5X) = 1/6 X²+5X = 6(2X+5) X²-7X-30=0 Solving, X=10
Advertisement
Related Mcqs:
- P can finish a work in 18 days. Q can finish the same work in 15 days. Q worked for 10 days and left the job. how many days does P alone need to finish the remaining work?
- A. 8 B. 6 C. 4 D. 2...
- A and B can finish a work 30 days if they work together. They worked together for 20 days and then B left. A finished the remaining work in another 20 days. In how many days A alone can finish the work?
- A. 70 B. 50 C. 40 D. 60...
- 4 men and 2 woman can complete a work in 2 days. If 2 men alone take 5 days to complete the work, find the time taken by 2 women alone to complete the work.
- A. 15 days B. 10 days C. 8 days D. 20 days...
- C takes 6 days to complete half of a work and D takes 5 days to complete 1/3rd of the same work. They take turns to complete the task. If C works for the first 4 days, in how many days will D complete the rest of the work without the help of C?
- A. 10 days B. 12 days C. 8 days D. 9 days...
- A alone can finish a work in 10 days and B alone can do it in 15 days. If they work together and finish, then out of a total wages of Rs.75. A will get:___________?
- A. 35 Rs. B. 40 Rs. C. 45 Rs. D. None of these...
- A and B together can complete a work in 1.2 days,. A alone can complete it in 20 days. If B does the work only for half a day daily, then in how many days A and B together will complete the work ?
- A. 10 days B. 11 days C. 15 days D. 20 days...
- A and B can finish a piece of work in 20 days .B and C in 30 days and C and A in 40 days. In how many days will A alone finish the job?
- A. 48 B. 34(2/7) C. 44 D. 45...
- P and Q can do a work in 30 days. Q and R can do the same work in 24 days and R and P in 20 days. They started the work together, but Q and R left after 10 days. How many days more will P take to finish the work?
- A. 10 B. 8 C. 18 D. 19...
- P and Q need 8 days to complete a work. Q and R need 12 days to complete the same work. But P, Q and R together can finish it in 6 days. How many days will be needed if P and R together do it?
- A. 7 B. 8 C. 9 D. 10...
- Farjan and Kashif can complete a task in 30 days. Farjan leaves after 20 days and Kashif alone completes it in another 25 days. How many days does Farjan alone take to complete the entire task?
- A. 50 B. 75 C. 60 D. 45...
Advertisement