Let work done by P in 1 day = p
work done by Q in 1 day =q
Work done by R in 1 day = r
p + q = 1/8 —(1)
q + r= 1/12 —(2)
p+ q+ r = 1/6 —(3)
(3) – (2) => p = 1/6 – 1/12 = 1/12
(3) – (1) => r = 1/6 – 1/8 = 1/24
p + r = 1/12 + 1/24 = 3/24 = 1/8
=> P and R will finish the work in 8 days
Advertisement
Related Mcqs:
- P can finish a work in 18 days. Q can finish the same work in 15 days. Q worked for 10 days and left the job. how many days does P alone need to finish the remaining work?
- A. 8 B. 6 C. 4 D. 2...
- C takes 6 days to complete half of a work and D takes 5 days to complete 1/3rd of the same work. They take turns to complete the task. If C works for the first 4 days, in how many days will D complete the rest of the work without the help of C?
- A. 10 days B. 12 days C. 8 days D. 9 days...
- A and B can finish a work 30 days if they work together. They worked together for 20 days and then B left. A finished the remaining work in another 20 days. In how many days A alone can finish the work?
- A. 70 B. 50 C. 40 D. 60...
- A alone can finish a work in X days. B alone can finish the same work in X+5 days. Together, they take 6 days to complete the work. Find X
- A. 12 B. 8 C. 10 D. 9...
- P and Q can do a work in 30 days. Q and R can do the same work in 24 days and R and P in 20 days. They started the work together, but Q and R left after 10 days. How many days more will P take to finish the work?
- A. 10 B. 8 C. 18 D. 19...
- 8 children and 12 men complete a certain piece of work in 9 days. If each child takes twice the time taken by a man to finish the work, in how many days will 12 men finish the same work ?
- A. 6 days B. 8 days C. 10 days D. 12 days...
- A and B together can complete a work in 1.2 days,. A alone can complete it in 20 days. If B does the work only for half a day daily, then in how many days A and B together will complete the work ?
- A. 10 days B. 11 days C. 15 days D. 20 days...
- 10 men can complete a work in 7 days. But 10 women need 14 days to complete the same work. How many days will 5 men and 10 women need to complete the work?
- A. 7 B. 5 C. 6 D. 4...
- 3 men and 7 women can complete a work in 10 days . But 4 men and 6 women need 8 days to complete the same work . In how many days will 10 women complete the same work?
- A. 50 B. 30 C. 40 D. 13...
- A and B can finish a piece of work in 20 days .B and C in 30 days and C and A in 40 days. In how many days will A alone finish the job?
- A. 48 B. 34(2/7) C. 44 D. 45...
Advertisement