A. 7
B. 5
C. 6
D. 4
Work done by 10 men in 1 day = 1/7
Work done by 1 man in 1 day = (1/7)/10 = 1/70
Work done by 10 women in 1 day = 1/14
Work done by 1 woman in 1 day = 1/140
Work done by 5 men and 10 women in 1 day = 5 × (1/70) + 10 × (1/140)
= 5/70 + 10/140 = 1/7
=> 5 men and 10 women can complete the work in 7 days
Advertisement
Related Mcqs:
- 3 men and 7 women can complete a work in 10 days . But 4 men and 6 women need 8 days to complete the same work . In how many days will 10 women complete the same work?
- A. 50 B. 30 C. 40 D. 13...
- C takes 6 days to complete half of a work and D takes 5 days to complete 1/3rd of the same work. They take turns to complete the task. If C works for the first 4 days, in how many days will D complete the rest of the work without the help of C?
- A. 10 days B. 12 days C. 8 days D. 9 days...
- 6 men and 8 women can complete a work in 10 days. 26 men and 48 women can finish the same work in 2 days. 15 men and 20 women can do the same work in_______days.
- A. 4 days B. 6 days C. 2 days D. 8 days...
- 4 men and 2 woman can complete a work in 2 days. If 2 men alone take 5 days to complete the work, find the time taken by 2 women alone to complete the work.
- A. 15 days B. 10 days C. 8 days D. 20 days...
- A and B together can complete a work in 1.2 days,. A alone can complete it in 20 days. If B does the work only for half a day daily, then in how many days A and B together will complete the work ?
- A. 10 days B. 11 days C. 15 days D. 20 days...
- If 12 men work 8 hours a day to complete a work in 10 days, how many men working 12 hours a day can complete the work in 5 days?
- A. 16 B. 4 C. 12 D. 8...
- P and Q can do a work in 30 days. Q and R can do the same work in 24 days and R and P in 20 days. They started the work together, but Q and R left after 10 days. How many days more will P take to finish the work?
- A. 10 B. 8 C. 18 D. 19...
- A,B,C, can do a work in 8,14,16 days respectively. A does the work for the first 2 days. B continues from it and finishes 2/3rd of the remaining work. C finishes the remaining work. How many days would have taken to complete the work?
- A. 13 B. 11 C. 12 D. 15...
- P and Q need 8 days to complete a work. Q and R need 12 days to complete the same work. But P, Q and R together can finish it in 6 days. How many days will be needed if P and R together do it?
- A. 7 B. 8 C. 9 D. 10...
- If 6 men take 9 days to complete a work, how many men can complete the work in 3 days?
- A. 2 men B. 12 men C. 9 men D. 18 men...
Advertisement