A. 35 Rs.
B. 40 Rs.
C. 45 Rs.
D. None of these
Ratio of time taken by A and B= 10 : 15 = 2 : 3
Ratio of work done in the same time = 3:2, So, the money is to be divided among A and B in the ratio 3 : 2
A’s share = Rs. [75×3/5] = Rs.45.
Related Mcqs:
- P can finish a work in 18 days. Q can finish the same work in 15 days. Q worked for 10 days and left the job. how many days does P alone need to finish the remaining work?
A. 8
B. 6
C. 4
D. 2 - A and B can finish a work 30 days if they work together. They worked together for 20 days and then B left. A finished the remaining work in another 20 days. In how many days A alone can finish the work?
A. 70
B. 50
C. 40
D. 60 - A alone can finish a work in X days. B alone can finish the same work in X+5 days. Together, they take 6 days to complete the work. Find X
A. 12
B. 8
C. 10
D. 9 - A and B can finish a piece of work in 20 days .B and C in 30 days and C and A in 40 days. In how many days will A alone finish the job?
A. 48
B. 34(2/7)
C. 44
D. 45 - P and Q can do a work in 30 days. Q and R can do the same work in 24 days and R and P in 20 days. They started the work together, but Q and R left after 10 days. How many days more will P take to finish the work?
A. 10
B. 8
C. 18
D. 19 - P takes twice as much time as Q or thrice as much time as R to finish a piece of work. They can finish the work in 2 days if work together. How much time will Q take to do the work alone?
A. 7
B. 8
C. 9
D. 6
Let P takes x days to complete the work
Then Q takes x/2 days and R takes x/3 days to finish the work
Amount of work P does in 1 day = 1/x
Amount of work Q does in 1 day = 2/x
Amount of work R does in 1 day = 3/x
Amount of work P,Q and R do in 1 day = 1/x + 2/x + 3/x = 1/x (1 + 2 + 3) = 6/x
6/x = 2
=> x = 12
=> Q takes 12/2 days = 6 days to complete the work - P can do a work in the same time in which Q and R together can do it. If P and Q work together, the work can be completed in 10 days. R alone needs 50 days to complete the same work. then Q alone can do it in__________?
A. 30 days
B. 25 days
C. 20 days
D. 15 days - 8 children and 12 men complete a certain piece of work in 9 days. If each child takes twice the time taken by a man to finish the work, in how many days will 12 men finish the same work ?
A. 6 days
B. 8 days
C. 10 days
D. 12 days - A completes 80% of a work in 20 days. Then B also joins and A and B together finish the remaining work in 3 days. How long does it need for B if he alone completes the work?
A. 37 ½ days
B. 22 days
C. 31 days
D. 22 days - A and B can complete a work in 15 days and 10 days respectively. They started doing the work together but after 2 days B had to leave and A alone completed the remaining work. The whole work was completed in___________?
A. 8 days
B. 10 days
C. 12 days
D. 15 days