A. 35 Rs.
B. 40 Rs.
C. 45 Rs.
D. None of these
Ratio of time taken by A and B= 10 : 15 = 2 : 3
Ratio of work done in the same time = 3:2, So, the money is to be divided among A and B in the ratio 3 : 2
A’s share = Rs. [75×3/5] = Rs.45.
Advertisement
Related Mcqs:
- P can finish a work in 18 days. Q can finish the same work in 15 days. Q worked for 10 days and left the job. how many days does P alone need to finish the remaining work?
- A. 8 B. 6 C. 4 D. 2...
- A and B can finish a work 30 days if they work together. They worked together for 20 days and then B left. A finished the remaining work in another 20 days. In how many days A alone can finish the work?
- A. 70 B. 50 C. 40 D. 60...
- A alone can finish a work in X days. B alone can finish the same work in X+5 days. Together, they take 6 days to complete the work. Find X
- A. 12 B. 8 C. 10 D. 9...
- A and B can finish a piece of work in 20 days .B and C in 30 days and C and A in 40 days. In how many days will A alone finish the job?
- A. 48 B. 34(2/7) C. 44 D. 45...
- P and Q can do a work in 30 days. Q and R can do the same work in 24 days and R and P in 20 days. They started the work together, but Q and R left after 10 days. How many days more will P take to finish the work?
- A. 10 B. 8 C. 18 D. 19...
- P takes twice as much time as Q or thrice as much time as R to finish a piece of work. They can finish the work in 2 days if work together. How much time will Q take to do the work alone?
- A. 7 B. 8 C. 9 D. 6 Let P takes x days to complete the work Then Q takes x/2 days and R takes x/3 days to finish the work Amount of work P does in 1 day = 1/x Amount of work Q does in 1 day = 2/x Amount of work R does in 1 day...
- P can do a work in the same time in which Q and R together can do it. If P and Q work together, the work can be completed in 10 days. R alone needs 50 days to complete the same work. then Q alone can do it in__________?
- A. 30 days B. 25 days C. 20 days D. 15 days...
- 8 children and 12 men complete a certain piece of work in 9 days. If each child takes twice the time taken by a man to finish the work, in how many days will 12 men finish the same work ?
- A. 6 days B. 8 days C. 10 days D. 12 days...
- A completes 80% of a work in 20 days. Then B also joins and A and B together finish the remaining work in 3 days. How long does it need for B if he alone completes the work?
- A. 37 ½ days B. 22 days C. 31 days D. 22 days...
- A and B can complete a work in 15 days and 10 days respectively. They started doing the work together but after 2 days B had to leave and A alone completed the remaining work. The whole work was completed in___________?
- A. 8 days B. 10 days C. 12 days D. 15 days...
Advertisement