A. 5
B. 6
C. 7
D. 8
Part of work completed by A in a day = 1/21 Part of work completed by B in a day = 1/24 Part of work completed by them together in a day = (1/21)+(1/24)
= 5/56 Part of work completed by B in 9 days
= 9/24 = 3/8 If A left after x days,
(5x/56)+(3/8) = 1
x = 7
Advertisement
Related Mcqs:
- Farjan and Kashif can complete a task in 30 days. Farjan leaves after 20 days and Kashif alone completes it in another 25 days. How many days does Farjan alone take to complete the entire task?
- A. 50 B. 75 C. 60 D. 45...
- P can do a work in 24 days. Q can do the same work in 9 days and R can do the same in 12 days. Q and R start the work and leave after 3 days. P finishes the remaining work in_________days.
- A. 10 B. 9 C. 11 D. 12...
- C takes 6 days to complete half of a work and D takes 5 days to complete 1/3rd of the same work. They take turns to complete the task. If C works for the first 4 days, in how many days will D complete the rest of the work without the help of C?
- A. 10 days B. 12 days C. 8 days D. 9 days...
- A completes 80% of a work in 20 days. Then B also joins and A and B together finish the remaining work in 3 days. How long does it need for B if he alone completes the work?
- A. 37 ½ days B. 22 days C. 31 days D. 22 days...
- A and B can complete a work in 15 days and 10 days respectively. They started doing the work together but after 2 days B had to leave and A alone completed the remaining work. The whole work was completed in___________?
- A. 8 days B. 10 days C. 12 days D. 15 days...
- X and Y can do a piece of work in 20 days and 12 days respectively. X started the work alone and then after 4 days Y joined him till the completion of the work. How long did the work last ?
- A. 6 days B. 10 days C. 15 days D. 20 days...
- P and Q can do a work in 30 days. Q and R can do the same work in 24 days and R and P in 20 days. They started the work together, but Q and R left after 10 days. How many days more will P take to finish the work?
- A. 10 B. 8 C. 18 D. 19...
- A,B,C, can do a work in 8,14,16 days respectively. A does the work for the first 2 days. B continues from it and finishes 2/3rd of the remaining work. C finishes the remaining work. How many days would have taken to complete the work?
- A. 13 B. 11 C. 12 D. 15...
- P is able to do a piece of work in 15 days and Q can do the same work in 20 days. If they can work together for 4 days, what is the fraction of work left?
- A. 8/15 B. 7/15 C. 11/15 D. 2/11...
- A and B together take 6 days to complete a task. B and C together take 12 days to complete the same task. A and C together take 8 days to complete it. If A, B and C are working together, how long does it take for them to complete the task?
- A. 4(2/3) days B. 4 days C. 5(1/3) days D. 1(1/3) days...
Advertisement