A. 3 days
B. 4 days
C. 6 days
D. 8 days
Submitted by: মোঃ আশাদুজ্জামান
Advertisement
Solution:
12×16×C=12×8×A
Or, A:C=2:1 [Efficiency ratio]
Let, Required time be T days
Applying MDH Method:
12×8×2=16×2×3+(6×2+4×1)×T
Or, 192=96+14T
Or, T=6
Answer:6 days
Related Mcqs:
- A can complete a work in 12 days with a working of 8 hours per day. B can complete the same work in 8 days when working 10 hours a day. If A and B work together, working 8 hours a day, the work can be completed in_______days.
- A. 5 5⁄11 B. 4 5⁄11 C. 6 4⁄11 D. 6 5⁄11...
- A and B can complete a work in 15 days and 10 days respectively. They started doing the work together but after 2 days B had to leave and A alone completed the remaining work. The whole work was completed in___________?
- A. 8 days B. 10 days C. 12 days D. 15 days...
- A,B,C, can do a work in 8,14,16 days respectively. A does the work for the first 2 days. B continues from it and finishes 2/3rd of the remaining work. C finishes the remaining work. How many days would have taken to complete the work?
- A. 13 B. 11 C. 12 D. 15...
- C takes 6 days to complete half of a work and D takes 5 days to complete 1/3rd of the same work. They take turns to complete the task. If C works for the first 4 days, in how many days will D complete the rest of the work without the help of C?
- A. 10 days B. 12 days C. 8 days D. 9 days...
- P and Q can complete a work in 15 days and 10 days respectively. They started the work together and then Q left after 2 days. P alone completed the remaining work. The work was finished in__________days.
- A. 12 B. 15 C. 22 D. 20...
- Twenty women can do a work in sixteen days. Sixteen men can complete the same work in fifteen days. What is the ratio between the capacity of a man and a woman ?
- A. 3 : 4 B. 4 : 3 C. 5 : 3 D. Data inadequate...
- A and B together take 6 days to complete a task. B and C together take 12 days to complete the same task. A and C together take 8 days to complete it. If A, B and C are working together, how long does it take for them to complete the task?
- A. 4(2/3) days B. 4 days C. 5(1/3) days D. 1(1/3) days...
- A and B together can complete a work in 1.2 days,. A alone can complete it in 20 days. If B does the work only for half a day daily, then in how many days A and B together will complete the work ?
- A. 10 days B. 11 days C. 15 days D. 20 days...
- 10 men can complete a work in 7 days. But 10 women need 14 days to complete the same work. How many days will 5 men and 10 women need to complete the work?
- A. 7 B. 5 C. 6 D. 4...
- 3 men and 7 women can complete a work in 10 days . But 4 men and 6 women need 8 days to complete the same work . In how many days will 10 women complete the same work?
- A. 50 B. 30 C. 40 D. 13...
Advertisement