A can complete the work in 12 days working 8 hours a day
=> Number of hours A can complete the work = 12×8 = 96 hours
=> Work done by A in 1 hour = 1/96
B can complete the work in 8 days working 10 hours a day
=> Number of hours B can complete the work = 8×10 = 80 hours
=> Work done by B in 1 hour = 1/80
Work done by A and B in 1 hour = 1/96 + 1/80 = 11/480
=> A and B can complete the work in 480/11 hours
A and B works 8 hours a day
Hence total days to complete the work with A and B working together
= (480/11)/ (8) = 60/11 days = 5 5⁄11 days
Mathematics Mcqs - Maths Mcqs are very important for every test. prepare for NTS, FPSC, PPSC, SPSC, CSS, PMS Test Preparation. and all other testing services. Most of the test syllabus contain Mathematics test portion. Here you will find most important Mathematics Mcqs. here these Mcqs will help you getting good marks in this Section. Here you will find most important Mcqs of Mathematics from Basic to Advance. some of the most important sub categories are: Average, Percentage, Problem on Ages, Time and Distance, HCF and LCM, Logarithms, Discount, Interest, Ratio & Proportion, Decimal Fraction and other.