A. 24 days
B. 14 days
C. 15 days
D. 20 days
Time and Men are inversely proportional. Time taken by 28 men to finish the work = 15 days Time taken by a man to finish the work
= 15*28 days Time taken by 21 men = (15*28)/21 = 20 days
Advertisement
Related Mcqs:
- P can finish a work in 18 days. Q can finish the same work in 15 days. Q worked for 10 days and left the job. how many days does P alone need to finish the remaining work?
- A. 8 B. 6 C. 4 D. 2...
- A and B can finish a work 30 days if they work together. They worked together for 20 days and then B left. A finished the remaining work in another 20 days. In how many days A alone can finish the work?
- A. 70 B. 50 C. 40 D. 60...
- 8 children and 12 men complete a certain piece of work in 9 days. If each child takes twice the time taken by a man to finish the work, in how many days will 12 men finish the same work ?
- A. 6 days B. 8 days C. 10 days D. 12 days...
- P and Q can do a work in 30 days. Q and R can do the same work in 24 days and R and P in 20 days. They started the work together, but Q and R left after 10 days. How many days more will P take to finish the work?
- A. 10 B. 8 C. 18 D. 19...
- A alone can finish a work in X days. B alone can finish the same work in X+5 days. Together, they take 6 days to complete the work. Find X
- A. 12 B. 8 C. 10 D. 9...
- 6 men and 8 women can complete a work in 10 days. 26 men and 48 women can finish the same work in 2 days. 15 men and 20 women can do the same work in_______days.
- A. 4 days B. 6 days C. 2 days D. 8 days...
- A and B can finish a piece of work in 20 days .B and C in 30 days and C and A in 40 days. In how many days will A alone finish the job?
- A. 48 B. 34(2/7) C. 44 D. 45...
- P takes twice as much time as Q or thrice as much time as R to finish a piece of work. They can finish the work in 2 days if work together. How much time will Q take to do the work alone?
- A. 7 B. 8 C. 9 D. 6 Let P takes x days to complete the work Then Q takes x/2 days and R takes x/3 days to finish the work Amount of work P does in 1 day = 1/x Amount of work Q does in 1 day = 2/x Amount of work R does in 1 day...
- P and Q need 8 days to complete a work. Q and R need 12 days to complete the same work. But P, Q and R together can finish it in 6 days. How many days will be needed if P and R together do it?
- A. 7 B. 8 C. 9 D. 10...
- A alone can finish a work in 10 days and B alone can do it in 15 days. If they work together and finish, then out of a total wages of Rs.75. A will get:___________?
- A. 35 Rs. B. 40 Rs. C. 45 Rs. D. None of these...
Advertisement