A. specialisation exists
B. machines are arranged according to sequence of operation
C. few number of non-standardised units are to be produced
D. mass production is envisaged
E. bought out items are more
Mechanical Engineering Mcqs
Mechanical Engineering Mcqs for Preparation of Job Test and interview, freshers, Students, competitive exams etc. Multiple choice questions here are on topics such as Machine Design, Theory of Machines, Hydraulic Machines etc.
| MECHANICAL ENGINEERING MCQS | |||
|---|---|---|---|
| 1. | Engineering Materials | 2. | Engineering Mechanics |
| 3. | Fluid Mechanics | 4. | Heat Transfer |
| 5. | Hydraulic Machines | 6. | I.C. Engines |
| 7. | Machine Design | 8. | Nuclear Power Plants |
| 9. | Production Technology | 10. | Workshop Technology |
| 11. | Refrigeration and Air Conditioning | 12. | Steam Boilers, Engines, Nozzles and Turbines |
| 13. | Compressors, Gas Turbines and Jet Engines | 14. | Strength of Materials |
| 15. | Theory of Machines | 16. | Thermodynamics |
A. batch production
B. continuous production
C. effective utilization of machine
D. all of the above
E. none of the above
A. have full flexibility
B. employ conveyor belts, trucks, tractors etc.
C. be a general purpose type
D. be designed as special purpose for a particular application
E. arranging shops according to specialization of duties
A. analysis of process chart
B. flow of material
C. ordering schedule of job
D. controlling inventory costs money
E. all of the above
Choose the wrong statement?
A. improving a work method
B. improvising a work method
C. designing a work method
D. providing a schematic framework
E. reducing inventory costs
A. 0.0001 minute
B. 0.0006 minute
C. 0.006 minute
D. 0.001 minute
E. 0.06 minute
A. the appraisal, in terms of time, of the value of work involving human effort
B. machine setting time
C. time taken by workers to do a job
D. method of fixing time for workers
E. method of determining the personnel Requirement
A. work sampling
B. time study
C. method study
D. work study
E. ABC analysis
A. relative worth of jobs
B. skills required by a worker
C. contribution of a worker
D. contribution of a job
E. effectiveness of various alternatives
A. operator’s activity
B. flow of material and in case of trouble locate source of trouble
C. minimising the delays
D. making efficient despatching
E. none of the above