A. 20 to 25 mm
B. 50 to 75 mm
C. 75 to 100 mm
D. 100 to 120 mm
Civil Engineering Mcqs
Civil Engineering Mcqs for Preparation of Job Test and interview, freshers, Students, competitive exams etc. Multiple choice questions here are on topics such as Building Construction, Materials for Construction, Basic Surveying, Highway Engineering, Dams, Airport Engineering, Structural Analysis etc.
A. sheet asphalt
B. bituminous carpet
C. mastic asphalt
D. rolled asphalt
A. bituminous carpet
B. mastic asphalt
C. sheet asphalt
D. bituminous bound macadam
A. sprayed after the aggregates are spread and compacted
B. premixed with aggregates and then spread
C. sprayed before the aggregates are spread and compacted
D. none of the above
A. sides and proceed to centre
B. centre and proceed to sides
C. one side and proceed to other side
D. any of the above
A. equal to the cross slope of pavement
B. less than the cross slope of pavement
C. greater than the cross slope of pavement
D. zero
A. granular soil
B. organic soil
C. silts
D. clays
A. smooth wheeled roller
B. pneumatic tyred roller
C. sheep foot roller
D. vibrator
A. seal coat
B. tack coat
C. prime coat
D. spray of emulsion
A. dry rolling, wet rolling, application of screening and application of filler
B. dry rolling, application of filler, wet rolling and application of screening
C. dry rolling, application of screening, wet rolling and application of filler
D. dry rolling, application of screening, application of filler and wet rolling