A. minor works
B. major works
C. large projects
D. all of the above
E. none of the above
Related Mcqs:
- Gnatt charts provide information about_____________?
A. break even point analysis
B. production schedule
C. material handling layout
D. determining selling price
E. value analysis - Gnatt charts are used for_________________?
A. forecasting sales
B. production schedule
C. scheduling and routing
D. linear programming
E. none of the above - Travel charts provide__________________?
A. an idea of the flow of materials at various stages
B. a compact estimate of the handling which must be done between various work sections
C. the information for changes required in rearranging material handling equipment
D. an approximate estimate of the handling which must be done at a particular station
E. solution to handling techniques to achieve most optimum^ results - A big advantage of PERT over Gantt charts is that in the former case_________________?
A. activities and events are clearly shown
B. early start and late finish of an activity are clearly marked
C. activity times are clear
D. critical path can be easily determined
E. inter-relationship among activities is clearly shown - Descripancies of bar chart techniques are________________?
A. consequential effects of lack in one activity on omer
B. consequential effects of lack in one activity on the finish date
C. free time available for an activity can’t be predicted
D. effective monitoring/controlling can’t be done
E. all of the above - For low load operation, more suitable (economical) engine is_______________?
A. S.I. engine
B. C.I. engine
C. both are equally good
D. multicylinder engine
E. two stroke engine - Cemented carbide tools are not found to be suitable for cutting_______________?
A. brass
B. cast iron
C. aluminium
D. steel
E. non-ferrous alloys. - In perpetual inventory control, the material is checked as it reaches its__________________?
A. minimum value
B. maximum value
C. average value
D. middle value
E. alarming value - CPM is the___________________?
A. time oriented technique
B. event oriented technique
C. activity oriented technique
D. target oriented technique
E. work oriented technique - The mathematical technique for finding the best use of limited resources in an optimum manner is known as___________________?
A. operation research
B. linear programming
C. network analysis
D. queuing theory
E. break-even analysis