A. Ordinary cuttings up to 1 m
B. Surface dressing up to 15 cm depths
C. Surface excavation up to 30 cm depths
D. Both B. and C.
Related Mcqs:
- The cost of the earthwork in excavation for the surface drain of cross-section shown in the given figure for a total length of 5 metres @ Rs. 450% cum, is_______________?
A. Rs. 400
B. Rs. 425
C. Rs. 450
D. Rs. 500 - The measurement is not made in square metres in case of________________?
A. D.P.C. (Damp proof course)
B. Form works
C. Concrete Jeffries
D. R.C. Chhajja - The excavation exceeding 1.5 m in width and 10 sq.m in plan area with a depth not exceeding 30 cm, is termed as_______________?
A. Excavation
B. Surface dressing
C. Cutting
D. Surface excavation - The expected out turn for earth work in excavation in ordinary soil per workman per day is_______________?
A. 1.00 cum
B. 2.00 cum
C. 3.00 cum
D. 4.00 cum - The reduced levels of points, 30 metres apart along the longitudinal section of a road portion between chainages 5 and 9 are shown in the given figure. If there is a uniform up-gradient of the road 120 in 1, the chainage of the point with no filling or cutting is__________________?
A. (6 + 15) chains
B. (6 + 12) chains
C. (6 + 18) chains
D. None of these - The rate of payment is made for 100 cu m (per % cu m) in case of__________________?
A. Earth work in excavation
B. Rock cutting
C. Excavation in trenches for foundation
D. All the above - The measurement is made in square metre in case of_________________?
A. Cement concrete in foundation
B. R.C.C. structure
C. Hollow concrete block wall
D. None of these - The concrete work for the following part of the building of specified thickness is measured in square metres_______________?
A. Root slabs
B. Floors
C. Wall panels
D. All the above - The measurement is made for stone work in square metre in case of________________?
A. Wall facing
B. Columns, lintels, copings
C. Building work
D. A. and D. of the above - Pick up the correct statement from the following?
A. In order to check up the average depth of excavation, ‘Dead man s’ are left at the mid-widths of borrow pits
B. The earthwork calculation in excavation is made from the difference in levels obtained with a level
C. The earth work in excavation to form the road embankment includes the formation of correct profile and depositing the soil in layers
D. All the above