A. Wall facing
B. Columns, lintels, copings
C. Building work
D. A. and D. of the above
Related Mcqs:
- The measurement is made in square metre in case of_________________?
A. Cement concrete in foundation
B. R.C.C. structure
C. Hollow concrete block wall
D. None of these - The measurement is not made in square metres in case of________________?
A. D.P.C. (Damp proof course)
B. Form works
C. Concrete Jeffries
D. R.C. Chhajja - The brick work is measured in sq metre, in case of_________________?
A. Honey comb brick work
B. Brick flat soling
C. Half brick walls or the partition
D. All the above - The concrete work for the following part of the building of specified thickness is measured in square metres_______________?
A. Root slabs
B. Floors
C. Wall panels
D. All the above - The brick work is not measured in cu m in case of_______________?
A. One or more than one brick wall
B. Brick work in arches
C. Reinforced brick work
D. Half brick wall - Pick up the excavation where measurements are made in square metres for payment ?
A. Ordinary cuttings up to 1 m
B. Surface dressing up to 15 cm depths
C. Surface excavation up to 30 cm depths
D. Both B. and C. - According to ISI method of measurement, the order of the sequence is_________________?
A. Length, breadth, height
B. Breadth, length, height
C. Height, length, breadth
D. None of these - The unit of measurement is per quintal for the following?
A. Collapsible gates with rails
B. Rolling shutters
C. Expanded metal wire netting
D. M.S. reinforcement of R.C.C. works
- The total length of a cranked bar through a distance D. at 45° in case of a beam of effective length L, is_________________?
A. L + 0.42 d
B. L + (2 × 0.42 d)
C. L – (0.42 d)
D. L – (2 × 0.4 d) - In case of laying gullies, siphons, intercepting traps, the cost includes_______________?
A. Setting and laying
B. Bed concreting
C. Connection to drains
D. All of these