A. 1.00 cum
B. 2.00 cum
C. 3.00 cum
D. 4.00 cum
Related Mcqs:
- The expected out turn of brick work in cement mortar in foundation and plinth per mason per day, is ________________?
A. 1.00 m3
B. 1.25 m3
C. 1.50 m3
D. 1.75 m3 - The expected out turn of cement concrete 1 : 2 : 4 per mason per day is_________________?
A. 1.5 m 3
B. 2.5 m3
C. 3.5 m3
D. 5.0 m3 - The expected out turn of 2.5 cm cement concrete floor per mansion per day__________________?
A. 2.5 sqm
B. 5.0 sqm
C. 7.5 sqm
D. 10 sqm - The expected out turn of half brick partition wall per mason per day is___________________?
A. 1.5 m 3
B. 2.0 m3
C. 4.0 m2
D. 5.0 m2 - The expected out turn of 12 mm plastering with cement mortar is_______________?
A. 2.5 sq m
B. 4.0 sq m
C. 6.0 sq m
D. 8.0 sq m - The cost of the earthwork in excavation for the surface drain of cross-section shown in the given figure for a total length of 5 metres @ Rs. 450% cum, is_______________?
A. Rs. 400
B. Rs. 425
C. Rs. 450
D. Rs. 500 - The excavation exceeding 1.5 m in width and 10 sq.m in plan area with a depth not exceeding 30 cm, is termed as_______________?
A. Excavation
B. Surface dressing
C. Cutting
D. Surface excavation - Pick up the excavation where measurements are made in square metres for payment ?
A. Ordinary cuttings up to 1 m
B. Surface dressing up to 15 cm depths
C. Surface excavation up to 30 cm depths
D. Both B. and C. - As per Indian Standard Specifications, the peak discharge for domestic purposes per capita per minute, is taken________________?
A. 1.80 litres for 5 to 10 users
B. 1.20 litres for 15 users
C. 1.35 for 20 users
D. All the above - The following item of earth work is not measured separately ?
A. Setting out of works
B. Site clearance
C. Steps in deep excavation
D. All the above