A. normal
B. binomial
C. beta
D. exponential
E. Gaussian
Related Mcqs:
- The probability distribution of activity times in PERT follows following distribution__________________?
A. normal
B. binomial
C. beta
D. exponential
E. Gaussian - PERT stands for k (fit) project evaluation and review technique__________________?
A. project examination and review technique
B. project evaluation and reporting technique
C. process execution and reporting technology
D. project execution and results technique - Positive slack on a PERT indicates that project is________________?
A. ahead of schedule
B. beyond schedule
C. as per schedule
D. on critical path
E. none of the above - PERT has following time estimate_________________?
A. one time estimate
B. two time estimate
C. three time estimate
D. four time estimate
E. nil time estimate - PERT/CPM, techniques can be used for following applications____________________?
A. once through project
B. maintenance jobs
C. research and development
D. all non-technical jobs
E. all of the above - PERT is the__________________?
A. time oriented technique
B. event oriented technique
C. activity oriented technique
D. target oriented technique
E. work oriented technique - PERT and CPM are__________________?
A. techniques to determine project status
B. decision making techniques
C. charts which increase aesthetic appearance of rooms
D. aids to determine cost implications of project
E. aids to the decision maker - Activity s,lack or float of any event on a PERT/CPM chart is represented by__________________?
A. latest start time of succeeding event -earliest finish time of preceding event activity time
B. latest start time of the event – earliest start time of the event
C. latest finish time of event – earliest finish time of the event
D. anyone of the above
E. none of the above - The important file in making a PERT is__________________?
A. an event can’t be accomplished until activities leading to it are completed
B. no activity from any event can be started from preceding event till it is completed
C. length of arrow has nothing to do with time
D. every activity must be completed before end point is reached
E. all of the above - The assumption in PERT is__________________?
A. a project will always be behind schedule, if left uncorrected
B. cost of project will always be more than the estimated cost, if no timely corrections are taken
C. a project can be subdivided into a set of predictable, independent activities
D. activities are fixed and can’t be changed ,
E. commissioning time can be changed, if activities are behind schedule