A. 4
B. 9.6
C. 9
D. 10
Part of work completed by A and B in 4 days
= 4*((1/16) + (1/12))
= 7/12 C can complete 5/12th of the work in 4 days C can complete the whole job in
4÷(5/12) = 9.6 days
Advertisement
Related Mcqs:
- P can lay railway track between two stations in 16 days. Q can do the same job in 12 days. With the help of R, they completes the job in 4 days. How much days does it take for R alone to complete the work?
A. 9(3/5) days
B. 9(1/5) days
C. 9(2/5) days
D. 10 days - Farjan and Kashif can complete a task in 30 days. Farjan leaves after 20 days and Kashif alone completes it in another 25 days. How many days does Farjan alone take to complete the entire task?
A. 50
B. 75
C. 60
D. 45 - A and B can finish a piece of work in 20 days .B and C in 30 days and C and A in 40 days. In how many days will A alone finish the job?
A. 48
B. 34(2/7)
C. 44
D. 45 - P can finish a work in 18 days. Q can finish the same work in 15 days. Q worked for 10 days and left the job. how many days does P alone need to finish the remaining work?
A. 8
B. 6
C. 4
D. 2 - A can do a certain work-in the same time in which B and C together can do it. If A and B together could do it in 10 days and C alone in 50 days, then B alone could do it in_________?
A. 15 days
B. 20 days
C. 25 days
D. 30 days - A alone can finish a work in X days. B alone can finish the same work in X+5 days. Together, they take 6 days to complete the work. Find X
A. 12
B. 8
C. 10
D. 9 - A and B can together do a piece of work in 15 days. B alone can do it in 20 days. In how many days can A alone do it ?
A. 40 days
B. 50 days
C. 60 days
D. 70 days - A and B can finish a work 30 days if they work together. They worked together for 20 days and then B left. A finished the remaining work in another 20 days. In how many days A alone can finish the work?
A. 70
B. 50
C. 40
D. 60 - 4 men and 2 woman can complete a work in 2 days. If 2 men alone take 5 days to complete the work, find the time taken by 2 women alone to complete the work.
A. 15 days
B. 10 days
C. 8 days
D. 20 days - A alone can finish a work in 10 days and B alone can do it in 15 days. If they work together and finish, then out of a total wages of Rs.75. A will get:___________?
A. 35 Rs.
B. 40 Rs.
C. 45 Rs.
D. None of these
Advertisement