A. 32 hours
B. 48 hours
C. 3 days
D. 4 days
Part of task completed by A in a day = 1/x Part of task completed by B in a day = 3/x (B is thrice as efficient as A) (1/x)+(3/x) = 1 4/x = 1 x = 4 B completes 3/4th of the task in a day. He takes 4/3 days to complete the entire task. 4/3 days = (4/3*24) hours = 32 hours
Related Mcqs:
- A and B together take 6 days to complete a task. B and C together take 12 days to complete the same task. A and C together take 8 days to complete it. If A, B and C are working together, how long does it take for them to complete the task?
A. 4(2/3) days
B. 4 days
C. 5(1/3) days
D. 1(1/3) days - Jameel can complete a task in 15 hours and Nasir can complete the same task in 12 hours. Jameel starts the task at 9:00 am and stops working at 2:00pm. Nasir starts working on the task at 4:00 pm. At what time is the task completed?
A. 12:00 pm
B. 2:00 am
C. 12:00 am
D. 10:00 pm - 4 men and 2 woman can complete a work in 2 days. If 2 men alone take 5 days to complete the work, find the time taken by 2 women alone to complete the work.
A. 15 days
B. 10 days
C. 8 days
D. 20 days - Farjan and Kashif can complete a task in 30 days. Farjan leaves after 20 days and Kashif alone completes it in another 25 days. How many days does Farjan alone take to complete the entire task?
A. 50
B. 75
C. 60
D. 45 - C takes 6 days to complete half of a work and D takes 5 days to complete 1/3rd of the same work. They take turns to complete the task. If C works for the first 4 days, in how many days will D complete the rest of the work without the help of C?
A. 10 days
B. 12 days
C. 8 days
D. 9 days - A and B together can complete a work in 1.2 days,. A alone can complete it in 20 days. If B does the work only for half a day daily, then in how many days A and B together will complete the work ?
A. 10 days
B. 11 days
C. 15 days
D. 20 days - P can do a work in the same time in which Q and R together can do it. If P and Q work together, the work can be completed in 10 days. R alone needs 50 days to complete the same work. then Q alone can do it in__________?
A. 30 days
B. 25 days
C. 20 days
D. 15 days - A alone can finish a work in X days. B alone can finish the same work in X+5 days. Together, they take 6 days to complete the work. Find X
A. 12
B. 8
C. 10
D. 9 - A and B can complete a work in 15 days and 10 days respectively. They started doing the work together but after 2 days B had to leave and A alone completed the remaining work. The whole work was completed in___________?
A. 8 days
B. 10 days
C. 12 days
D. 15 days - P and Q can complete a work in 20 days and 12 days respectively. P alone started the work and Q joined him after 4 days till the completion of the work. How long did the work last?
A. 5 days
B. 10 days
C. 15 days
D. 12 days