A. 5 days
B. 10 days
C. 15 days
D. 12 days
Work done by P in 1 day = 1/20
Work done by Q in 1 day = 1/12
Work done by P in 4 days = 4 × (1/20) = 1/5
Remaining work = 1 – 1/5 = 4/5
Work done by P and Q in 1 day = 1/20 + 1/12 = 8/60 = 2/15
Number of days P and Q take to complete the remaining work = (4/5) / (2/15) = 6
Total days = 4 + 6 = 10
Advertisement
Related Mcqs:
- X and Y can do a piece of work in 20 days and 12 days respectively. X started the work alone and then after 4 days Y joined him till the completion of the work. How long did the work last ?
- A. 6 days B. 10 days C. 15 days D. 20 days...
- 4 men and 2 woman can complete a work in 2 days. If 2 men alone take 5 days to complete the work, find the time taken by 2 women alone to complete the work.
- A. 15 days B. 10 days C. 8 days D. 20 days...
- A and B can complete a work in 15 days and 10 days respectively. They started doing the work together but after 2 days B had to leave and A alone completed the remaining work. The whole work was completed in___________?
- A. 8 days B. 10 days C. 12 days D. 15 days...
- P and Q can complete a work in 15 days and 10 days respectively. They started the work together and then Q left after 2 days. P alone completed the remaining work. The work was finished in__________days.
- A. 12 B. 15 C. 22 D. 20...
- C takes 6 days to complete half of a work and D takes 5 days to complete 1/3rd of the same work. They take turns to complete the task. If C works for the first 4 days, in how many days will D complete the rest of the work without the help of C?
- A. 10 days B. 12 days C. 8 days D. 9 days...
- A and B together can complete a work in 1.2 days,. A alone can complete it in 20 days. If B does the work only for half a day daily, then in how many days A and B together will complete the work ?
- A. 10 days B. 11 days C. 15 days D. 20 days...
- A alone can finish a work in X days. B alone can finish the same work in X+5 days. Together, they take 6 days to complete the work. Find X
- A. 12 B. 8 C. 10 D. 9...
- Farjan and Kashif can complete a task in 30 days. Farjan leaves after 20 days and Kashif alone completes it in another 25 days. How many days does Farjan alone take to complete the entire task?
- A. 50 B. 75 C. 60 D. 45...
- P can do a work in the same time in which Q and R together can do it. If P and Q work together, the work can be completed in 10 days. R alone needs 50 days to complete the same work. then Q alone can do it in__________?
- A. 30 days B. 25 days C. 20 days D. 15 days...
- Twelve children take sixteen days to complete a work which can be completed by 8 adults in 12 days. After working for 3 days, sixteen adults left and six adults and four children joined them. How many days will they take to complete the remaining work ?
- A. 3 days B. 4 days C. 6 days D. 8 days Submitted by: মোঃ আশাদুজ্জামান...
Advertisement