A. ISO 9000
B. CMM
C. CMMI
D. All of the mentioned
Explanation: It is defined in all the mentioned options.
Related Mcqs:
- Which of the following is incorrect activity for the configuration management of a software system ?
A. Internship management
B. Change management
C. Version management
D. System management - Which of the following option is not tracked by configuration management tools ?
A. Tracking of change proposals
B. Storing versions of system components
C. Tracking the releases of system versions to customers
D. None of the mentioned - Which of the following is not a Software Configuration Management Activity ?
A. Configuration item identification
B. Risk management
C. Release management
D. Branch management - Which is a software configuration management concept that helps us to control change without seriously impeding justifiable change ?
A. Baselines
B. Source code
C. Data model
D. None of the mentioned - Software Configuration Management can be administered in several ways. These include __________________?
A. A single software configuration management team for the whole organization
B. A separate configuration management team for each project
C. Software Configuration Management distributed among the project members
D. All of the mentioned - Quality planning is the process of developing a quality plan for__________________?
A. team
B. project
C. customers
D. project manager - Which of the following is a configuration item ?
A. Design & Test specification
B. Source code
C. Log information
D. All of the mentioned - What complements the formal technical review by assessing a configuration object for characteristics that are generally not considered during review ?
A. Software configuration audit
B. Software configuration management
C. Baseline
D. None of the mentioned - What combines procedures and tools to manage different versions of configuration objects that are created during the software process ?
A. Change control
B. Version control
C. SCIs
D. None of the mentioned - If a Direct approach to software project sizing is taken, size can be measured in__________________?
A. LOC
B. FP
C. LOC and FP
D. None of the mentioned