A. line organisation
B. line and staff organisation
C. functional organisation
D. all of the above
E. none of the above
Related Mcqs:
- The main advantage of line organisation is its_______________?
A. effective command and control
B. defined responsibilities at all levels
C. rigid discipline in the organisation
D. ability of quick decision at all levels
E. all of the above - The salient feature of functional organisation is________________?
A. strict adherence to specification
B. separation of planning and design part
C. each individual maintains functional efficiency
D. work is properly planned and distributed
E. all of the above - Which of the following organisation is preferred in automobile industry________________?
A. functional organisation
B. line organisation
C. staff organisation
D. line and staff organisations
E. scalar organisation - The most popular type of organisation used for Civil Engineering Constructions is_________________?
A. line organisation
B. line and staff organisation
C. functional organisation
D. effective organisation
E. none of the above - The main disadvantage of line organisation is_________________?
A. top level executives have to do excessive work
B. structure is rigid
C. communication delays occur
D. all of the above
E. none of the above - The time required to complete a job is established and a bonus is paid to the worker based on the exact % of time saved. This type of incentive plan is known as_________________?
A. Dry work Plan
B. Halsey Premium Plan
C. Taylor Plan
D. Bedaux Plan
E. Rowan Plan - The time required to complete a task is established and a bonus is paid to the worker for every hour he saves from the established time required. This type of incentive plan is known as_________________?
A. Rowan Plan
B. Bedaux Plan
C. Taylor Differential Piece rate system
D. Halsey Premium plan
E. Day work plan - The performance of a specific task in CPM is known as ______________________?
A. dummy
B. event
C. activity
D. contract
E. none of the above - The artificial activity; which indicates that an activity following it cannot be started unless, the preceding activity is complete, is known as_________________?
A. event
B. free float
C. artificial
D. constraint
E. dummy - The time by which the activity completion time can be delayed without affecting the start of succeeding activities, is Known as_________________?
A. duration
B. total float
C. free float
D. interfering float
E. none of the above