1. drilling and blasting
2. timbering
3. pumping
4. mucking
Select the correct answer using the codes given below Codes?
A. 1,2,3,4
B. 1,4,2,3
C. 2,1,4,3
D. 2,4,1,3
Related Mcqs:
- What is the correct sequence of the following events in rock tunnelling?
1. marking tunnel profile
2. loading explosives and blasting
3. checking misfire
4. mucking
5. removing foul gas
6. setting up and drilling
7. guniting
Select the correct answer using the codes given below
Codes ?A. 1,6,5,3,4,2,7
B. 1,2,6,3,5,4,7
C. 1, 6,2, 5,4, 3, 7
D. 1,6,2,5,3,4,7 - Assertion A : When rock conditions are favorable, it will not be necessary to take up concrete lining concurrently with the driving operations till the full length of the tunnel has been driven through rock. Reason R : A tunnel through rock, hard or soft, does not need any concrete lining________________?
A. Both A and R are true and R is the correct explanation of A
B. Both A and R are true but R is not the correct explanation of A
C. A is true but R is false
D. A is false but R is true - In the construction of Metro Railways, “Cut and Cover” method of construction is suitable in situations listed at________________?
Consider the following situations
1. Soil is soft
2. Volume of existing surface traffic on the alignment is heavy
3. Track is at a deeper level
4. Water table is highA. 1 and 2
B. 1 and 3
C. 1 and 4
D. 2 and 3 - The correct sequence of drilling equipment for increasing size of holes in tunnels is________________?
A. wagon drill, churn drill, shot drill
B. wagon drill, shot drill, churn drill
C. shot drill, churn drill, wagon drill
D. churn drill, wagon drill, shot drill - Which one of the following is considered to be an advantage of the heading and benching method of tunnel construction?
A. It is suitable for construction in unstable rocks
B. In this method, it is easy to install timber support
C. Tunnelling can be continuous and the work can be expedited
D. In case of excessive water, it is easy to take correct steps - If ‘N’ is the number of shafts used, then the total number of feces available for attacking the excavation and construction in tunnels are_________________________?
A. 2N
B. N + 2
C. 2 N + 1
D. 2 N + 2 - Which of the following lining material is useful for shield driven tunnels in sub aqueous regions ?
A. stone masonry
B. timber
C. cast iron
D. cement concrete - Which one of the following tunnelling methods is used for laying under ground sewers ?
A. Needle beam method
B. Army method
C. German method
D. Italian method - Which one of the following is a component of a shield for tunnelling ?
A. liner plate
B. trench jack
C. stiffener
D. cutting edge - Which of the following is not a component of the shield ?
A. propelling jacks
B. liner plate
C. hood
D. tail