A. 20 to 40 tonnes/hr
B. 50 to 100 tonnes/hr
C. 100 to 150 tonnes/hr
D. 150 to 200 tonnes/hr
Power Generation
Power Generation/ Power Plant Engineering
A. dust
B. clinkers
C. iron particles
D. sand
A. reduce the flame length
B. increase the flame length
C. transport and dry the coal
D. provide air round the burners for getting optimum combustion
A. reduce the flame length
B. increase the flame length
C. transport and dry the coal
D. provide air around burners for get¬ting optimum combustion
A. burn completely
B. burn freely
C. do not form ash
D. form lumps or masses of coke
A. 20 to 100 MW
B. 50 to 300 MW
C. 70 to 400 MW
D. 100 to 650 MW
A. 1 to 5%
B. 4 to 10%
C. 10 to 12%
A. 20 kgf/cm2
B. 50 kgf/cm2
C. 100 kgf/cm2
D. 150 kgf/cm2
A. center of coal fields
B. center of maximum load of equipments
C. center of gravity of electrical system
A. 25 to 30%
B. 40 to 50%
C. 65 to 70%
D. 85 to 90%