A. cumulative discharge and time
B. discharge and percentage probability of flow being equaled or exceeded
C. cumulative discharge, volume and time in chronological order
D. discharge and time in chronological order
Civil Engineering Mcqs
Civil Engineering Mcqs for Preparation of Job Test and interview, freshers, Students, competitive exams etc. Multiple choice questions here are on topics such as Building Construction, Materials for Construction, Basic Surveying, Highway Engineering, Dams, Airport Engineering, Structural Analysis etc.
A. V2 Q m3/sec
B. 0.5 Q mVsec
C. 2 Q m3/sec
D. 4 Q m3/sec
A. 4.5 cm
B. 6.0 cm
C. 7.5 cm
D. 9.0 cm
A. methyl alcohol
B. ethyl alcohol
C. cetyl alcohol
D. butyl alcohol
A. 100 mm
B. more than 100 mm
C. less than 100 mm
D. none of the above
A. rainfall intensity and time
B. rainfall depth and time
C. discharge and time
D. cumulative rainfall and time
A. load factor
B. plant factor
C. utilisation factor
D. both (A) and (B)
A. is a medium head scheme
B. generates power during peak hours only
C. is suitable only on a perennial river
D. has no pondage at all
A. a low head scheme
B. a medium head scheme
C. a high head scheme
D. none of the above
A. scouring on concave side
B. silting on convex side
C. scouring on convex side and on concave side
D. scouring on concave side and silting on convex side