A. 14
B. 88
C. 24
D. 68
Related Mcqs:
- If the residual error is 35 and the predicted cost value is 20, then the observed cost value will be _________?
A. 55
B. 15
C. 65
D. 85 - If the residual error is 25 and the predicted cost value is 50, then the observed cost value would be ______________?
A. 100
B. 25
C. 50
D. 75 - In Regression Analysis, if an observed cost value is 85 and the disturbance error is 25 then predicted cost value will be ___________?
A. 110
B. 125
C. 60
D. 70 - In Regression Analysis, if an observed cost value is 85 and the disturbance error is 25 then predicted cost value will be ___________?
A. 95
B. 50
C. 120
D. 100 - In regression analysis, if an observed cost value is 65 and the disturbance error is 32 then predicted cost value will be __________?
A. 97
B. 57
C. 33
D. 53 - In regression analysis, if the predicted cost value is 65 and observed cost value is 19 then the disturbance term will be __________?
A. 46
B. 56
C. 36
D. 76 - In regression analysis, if the observed cost value is 50 and predicted cost value is 7, then the disturbance term will be __________?
A. 57
B. 43
C. 67
D. 47 - In regression analysis, if the observed cost value is 62 and predicted cost value is 29, then the disturbance term would be ____________?
A. 33
B. 91
C. 81
D. 43 - Chemical engineering plant cost index is used for finding the present cost of a particular chemical plant, if the cost of similar plant at some time in the past is known. The present cost of the plant = original cost × (index value at present/ index value at time original cost was obtained). The most major component of this cost index is____________________?
A. Fabricated equipment and machinery
B. Process instruments and control
C. Pumps and compressor
D. Electrical equipments and material - An error term, disturbance term or residual term is calculated as ___________?
A. U=A-b
B. u=A-a
C. u=Y-y
D. u=X-x
Mcq Added by: Lubaba Zarshal