A. 1.00 m3
B. 1.25 m3
C. 1.50 m3
D. 1.75 m3
Related Mcqs:
- The expected out turn of half brick partition wall per mason per day is___________________?
A. 1.5 m 3
B. 2.0 m3
C. 4.0 m2
D. 5.0 m2 - The expected out turn of cement concrete 1 : 2 : 4 per mason per day is_________________?
A. 1.5 m 3
B. 2.5 m3
C. 3.5 m3
D. 5.0 m3 - The expected out turn of 12 mm plastering with cement mortar is_______________?
A. 2.5 sq m
B. 4.0 sq m
C. 6.0 sq m
D. 8.0 sq m - The expected out turn of 2.5 cm cement concrete floor per mansion per day__________________?
A. 2.5 sqm
B. 5.0 sqm
C. 7.5 sqm
D. 10 sqm - For 12 mm thick cement plastering 1 : 6 on 100 sq.m new brick work, the quantity of cement required, is___________________?
A. 0.200 m3
B. 0.247 m3
C. 0.274 m3
D. 0.295 m3 - The expected out turn for earth work in excavation in ordinary soil per workman per day is_______________?
A. 1.00 cum
B. 2.00 cum
C. 3.00 cum
D. 4.00 cum - Pick up the item of work not included in the plinth area estimate______________?
A. Wall thickness
B. Room area
C. W.C. area
D. Courtyard area - The plinth area of a building not includes_________________?
A. Area of the walls at the floor level
B. Internal shaft for sanitary installations up to 2 sq m. in area
C. Lift and wall including landing
D. Area of cantilevered porch - For 100 sq. m cement concrete (1 : 2: 4) 4 cm thick floor, the quantity of cement required, is_______________?
A. 0.90 m3
B. 0.94 m3
C. 0.98 m3
D. 1.00 m3 - The brick work is measured in sq metre, in case of_________________?
A. Honey comb brick work
B. Brick flat soling
C. Half brick walls or the partition
D. All the above