A. 2.5 sq m
B. 4.0 sq m
C. 6.0 sq m
D. 8.0 sq m
Related Mcqs:
- The expected out turn of brick work in cement mortar in foundation and plinth per mason per day, is ________________?
A. 1.00 m3
B. 1.25 m3
C. 1.50 m3
D. 1.75 m3 - For 12 mm thick cement plastering 1 : 6 on 100 sq.m new brick work, the quantity of cement required, is___________________?
A. 0.200 m3
B. 0.247 m3
C. 0.274 m3
D. 0.295 m3 - The expected out turn of cement concrete 1 : 2 : 4 per mason per day is_________________?
A. 1.5 m 3
B. 2.5 m3
C. 3.5 m3
D. 5.0 m3 - The expected out turn of 2.5 cm cement concrete floor per mansion per day__________________?
A. 2.5 sqm
B. 5.0 sqm
C. 7.5 sqm
D. 10 sqm - For 100 sq. m cement concrete (1 : 2: 4) 4 cm thick floor, the quantity of cement required, is_______________?
A. 0.90 m3
B. 0.94 m3
C. 0.98 m3
D. 1.00 m3 - The expected out turn for earth work in excavation in ordinary soil per workman per day is_______________?
A. 1.00 cum
B. 2.00 cum
C. 3.00 cum
D. 4.00 cum - The expected out turn of half brick partition wall per mason per day is___________________?
A. 1.5 m 3
B. 2.0 m3
C. 4.0 m2
D. 5.0 m2 - While estimating a reinforced cement structure, the omitted cover of concrete is assumed_______________?
A. At the end of reinforcing bar, not less than 25 mm or twice the diameter of the bar
B. In thin slabs, 12 mm minimum or diameter of the bar whichever is more
C. For reinforcing longitudinal bar in a beam 25 mm minimum or diameter of the largest bar which is more
D. All the above - A cement concrete road is 1000 m long, 8 m wide and 15 cm thick over the sub-base of 10 cm thick gravel. The box cutting in road crust is__________________?
A. 500 m3
B. 1000 m 3
C. 1500 m3
D. 2000 m3 - According to Indian Standards Institute, the actual size of modular bricks is_______________?
A. 23 cm × 11.5 cm × 7.5 cm
B. 25 cm × 13 cm × 7.5 cm
C. 19 cm × 9 cm × 9 cmD. 20 cm × 10 cm × 10 cm