A. It is suitable for construction in unstable rocks
B. In this method, it is easy to install timber support
C. Tunnelling can be continuous and the work can be expedited
D. In case of excessive water, it is easy to take correct steps
Related Mcqs:
- Assertion A : When rock conditions are favorable, it will not be necessary to take up concrete lining concurrently with the driving operations till the full length of the tunnel has been driven through rock. Reason R : A tunnel through rock, hard or soft, does not need any concrete lining________________?
A. Both A and R are true and R is the correct explanation of A
B. Both A and R are true but R is not the correct explanation of A
C. A is true but R is false
D. A is false but R is true - In the construction of Metro Railways, “Cut and Cover” method of construction is suitable in situations listed at________________?
Consider the following situations
1. Soil is soft
2. Volume of existing surface traffic on the alignment is heavy
3. Track is at a deeper level
4. Water table is highA. 1 and 2
B. 1 and 3
C. 1 and 4
D. 2 and 3 - If ‘D’ is the diameter of tunnel in meters, then the thickness of lining in mm, as per the empirical formula is given by_________________?
A. 42 D
B. 82 D
C. 104 D
D. 124 D - What is the correct sequence of the following events of construction of a shaft in rock ?
1. drilling and blasting
2. timbering
3. pumping
4. muckingSelect the correct answer using the codes given below Codes?
A. 1,2,3,4
B. 1,4,2,3
C. 2,1,4,3
D. 2,4,1,3 - Assertion A : English method of tunneling requires more time as compared to other methods of tunneling. Reason R : In English method of tunneling, the masons and excavators have to work alternately/
A. Both A and R are true and R is the correct explanation of A.
B. Both A and R are true and R is not the correct explanation of A.
C. A is true but R is false.
D. A is false but R is true. - If ‘N’ is the number of shafts used, then the total number of feces available for attacking the excavation and construction in tunnels are_________________________?
A. 2N
B. N + 2
C. 2 N + 1
D. 2 N + 2 - Drift method of tunnelling is used to construct tunnels in__________________?
A. soft grounds
B. rock
C. self supporting grounds
D. broken grounds - In Belgium method of tunneling _________________?
A. construction of side walls is completed before invert and roof arch are built
B. construction of roof arch is completed before side walls and invert are built
C. construction of invert is completed before side walls and roof arch are built
D. construction of invert and side walls is completed before roof arch is built - American method of tunneling________________?
i) is suitable for large sized tunnels
ii) is no,’ suitable for railway or highway tunnel’s
iii) requires heavy timbers
select the correct answer?A. only (i) is correct
B. (i) and (iii) are correct
C. (ii) and (iii) are correct
D. (i) and (ii) are correct - In “full face” method of constructing tunnels, the first operation relates to______________?
A. removal of bottom portion
B. excavation of one drift in the centre
C. removal of top portion
D. excavation being done along the periphery