A. SCM procedures
B. Source code
C. Software design descriptions
D. All of the mentioned
Explanation: All are covered in CM.
Related Mcqs:
- What is one or more software configuration items that have been formally reviewed and agreed upon and serve as a basis for further development ?
A. Configuration
B. Baseline
C. Software
D. All of the mentioned - Which of the following is not a part of Software Configuration Management Basics ?
A. Identification
B. Version
C. Auditing and Reviewing
D. Status Accounting - Which of the following is not a main phase in Configuration Management (CM) Process ?
A. CM Planning
B. Executing the CM process
C. CM audits
D. None of the mentioned - What is a specific instance of a baseline or configuration item ?
A. Software
B. Configuration
C. Version
D. Status Accounting - Which of the following is black box testing______________________?
A. Basic path testing
B. Boundary value analysis
C. Code path analysis
D. None of the mentioned - Which of the following is not regression test case ?
A. A representative sample of tests that will exercise all software functions
B. Additional tests that focus on software functions that are likely to be affected by the change
C. Tests that focus on the software components that have been changed
D. Low-level components are combined into clusters that perform a specific software sub-function - Which of the following is black-box oriented and can be accomplished by applying the same black-box methods discussed for conventional software ?
A. Conventional testing
B. OO system validation testing
C. Test case design
D. Both Conventional testing and OO system validation testing - Which of the following is a common pointwer problem ?
A. Data sharing errors
B. Accessing data elements of the wrong type
C. Attempting to use memory areas after freeing them
D. All of the mentioned - Which of the following is a software process ?
A. Analysis and design
B. Configuration and management
C. Business modeling
D. All of the mentioned - Which of the following is not a change management process ?
A. Log the changes
B. Estimate impact on effort and schedule
C. Review impact with stakeholders
D. None of the mentioned