A. Software Configuration Item
B. Baseline
C. Configuration
D. Configuration Control Board
Explanation: Configuration Control Board (CCB. is the group with the responsibility for reviewing and approving changes to baselines
Advertisement
Related Mcqs:
- How are baselines verified ?
- A. By reviews B. By inspections C. By testing of code D. All of the mentioned...
- According to ISO 9001, inspection and testing comes under which management responsibility ?
- A. Process control B. Document control C. Control of nonconforming products D. Servicing...
- The testing in which code is checked___________________?
- A. Black box testing B. White box testing C. Red box testing D. Green box testing...
- Testing done without planning and Documentation is called_________________?
- A. Unit testing B. Regression testing C. Adhoc testing D. None of the mentioned...
- Which of the following is not used in measuring the size of the software_____________________?
- A. KLOC B. Function Points C. Size of module D. None of the mentioned...
- The construction of object-oriented software begins with the creation of__________________?
- A. design model B. analysis model C. code levels D. both design and analysis model...
- Which of the following is not a part of Execution Flow during debugging ?
- A. Step Over B. Step Into C. Step Up D. Step Out...
- Software Testing with real data in real environment is known as_____________________?
- A. alpha testing B. beta testing C. regression testing D. none of the mentioned...
- Which of the following is not a typical environment in communication facilitation ?
- A. Multiple teams B. Multiple user groups C. Multiple fests D. Multiple locations...
- The degree to which the design specifications are followed during manufacturing is known as________________?
- A. Quality of design B. Quality of conformance C. Quality of testing D. None of the mentioned...