A. Specification delays
B. Product competition
C. Testing
D. Staff turnover
Explanation: Testing is a part of project, thus it can’t be categorized as risk.
Related Mcqs:
- What assess the risk and your plans for risk mitigation and revise these when you learn more about the risk ?
A. Risk monitoring
B. Risk planning
C. Risk analysis
D. Risk identification - What evaluates the risk associated with the technology to be implemented as part of project scope ?
A. Concept scoping
B. Preliminary concept planning
C. Technology risk assessment
D. Customer reaction to the concept - Which of the following is not project management goal ?
A. Keeping overall costs within budget
B. Delivering the software to the customer at the agreed time
C. Maintaining a happy and well-functioning development team
D. Avoiding customer complaints - Which of the following is not an effective software project management focus ?
A. people
B. product
C. popularity
D. process - Which one is not a risk management activity ?
A. Risk assessment
B. Risk generation
C. Risk control
D. None of the mentioned - Risk management is one of the most important jobs for a__________________?
A. Client
B. Investor
C. Production team
D. Project manager - Which of the following is not a project factor that should be considered when planning the structure of software engineering teams ?
A. The difficulty of the problem to be solved
B. High frustration caused by personal, business, or technological factors that causes friction among team members
C. The degree of sociability required for the project
D. The rigidity of the delivery date - A 66.6% risk is considered as__________________?
A. very low
B. low
C. moderate
D. high - Which of the following is not a business risk ?
A. building an excellent product or system that no one really wants
B. losing the support of senior management due to a change in focus or change in people
C. lack of documented requirements or software scope
D. losing budgetary or personnel commitment - Which of the following risk is the failure of a purchased component to perform as expected ?
A. Product risk
B. Project risk
C. Business risk
D. Programming risk