A. LOC
B. FP
C. Fuzzy Logic
D. LOC and FP
Explanation: A function point (FP) is a unit of measurement to express the amount of business functionality an information system provides to a user
Related Mcqs:
- If a Direct approach to software project sizing is taken, size can be measured in__________________?
A. LOC
B. FP
C. LOC and FP
D. None of the mentioned - Which software project sizing approach develop estimates of the information domain characteristics ?
A. Function point sizing
B. Change sizing
C. Standard component sizing
D. Fuzzy logic sizing - Who suggested the four different approaches to the sizing problem ?
A. Putnam
B. Myers
C. Boehm
D. Putnam and Myers - What can be used to complement decomposition techniques and offer a potentially valuable estimation approach in their own right ?
A. Automated estimation tools
B. Empirical estimation models
C. Decomposition techniques
D. Both Automated estimation tools and Empirical estimation models - A number of independent investigators have developed a team-oriented approach to requirements gathering that can be applied to establish the scope of a project called ?
A. JAD
B. CLASS
C. FAST
D. None of the mentioned - Which of the following is not an approach to software cost estimation ?
A. Empirical
B. Heuristic
C. Analytical
D. Critical - Which one is not a stage of COCOMO-II ?
A. Early design estimation model
B. Application Composition estimation model
C. Comprehensive cost estimation model
D. Post architecture estimation model - Which of the following term is best defined by the statement:”the degree of uncertainty that the product will meet its requirements and be fit for its intended use.”?
A. Performance risk
B. Cost risk
C. Support risk
D. Schedule risk - Which of the following is not one of the five information domain characteristics of Function Point (FP) decomposition ?
A. External inputs
B. External outputs
C. External process
D. External inquiries - What is used to determine the recommended degree of rigor with which the software process should be applied on a project ?
A. Degree of Rigor
B. Adaptation criteria
C. Task Set
D. Both degree of Rigor and adaptation criteria