Work done by P in 1 hour = 1/8
Work done by Q in 1 hour = 1/10
Work done by R in 1 hour = 1/12
Work done by P,Q and R in 1 hour = 1/8 + 1/10 + 1/12 = 37/120
Work done by Q and R in 1 hour = 1/10 + 1/12 = 22/120 = 11/60
From 9 am to 11 am, all the machines were operating.
Ie, they all operated for 2 hours and work completed = 2 × (37/120) = 37/60
Pending work = 1- 37/60 = 23/60
Hours taken by Q an R to complete the pending work = (23/60) / (11/60) = 23/11
which is approximately equal to 2
Hence the work will be completed approximately 2 hours after 11 am ; ie around 1 pm
Mathematics Mcqs - Maths Mcqs are very important for every test. prepare for NTS, FPSC, PPSC, SPSC, CSS, PMS Test Preparation. and all other testing services. Most of the test syllabus contain Mathematics test portion. Here you will find most important Mathematics Mcqs. here these Mcqs will help you getting good marks in this Section. Here you will find most important Mcqs of Mathematics from Basic to Advance. some of the most important sub categories are: Average, Percentage, Problem on Ages, Time and Distance, HCF and LCM, Logarithms, Discount, Interest, Ratio & Proportion, Decimal Fraction and other.