A. 1
B. 5
C. 10
D. 25
10 workers make 10 tables in 10 days. 1 worker makes 1 table in 10 days. Similarly, 5 workers can make 5 tables in 10 days.
Related Mcqs:
- The average of women and child workers in a factory was 15%yr. The average age of all the 16 children was 8yr and average age of women workers was 22 yrs if ten women workers were married then the number of unmarried women workers were________?
A. 16
B. 12
C. 8
D. 6 - P and Q can do a work in 30 days. Q and R can do the same work in 24 days and R and P in 20 days. They started the work together, but Q and R left after 10 days. How many days more will P take to finish the work?
A. 10
B. 8
C. 18
D. 19 - A and B can finish a piece of work in 20 days .B and C in 30 days and C and A in 40 days. In how many days will A alone finish the job?
A. 48
B. 34(2/7)
C. 44
D. 45 - A and B can do a piece of work in 21 and 24 days respectively.They start the work together and after some days, A leaves and B completes the rest of the task in 9 days. After how many days did A leave?
A. 5
B. 6
C. 7
D. 8 - P and Q need 8 days to complete a work. Q and R need 12 days to complete the same work. But P, Q and R together can finish it in 6 days. How many days will be needed if P and R together do it?
A. 7
B. 8
C. 9
D. 10 - Farjan and Kashif can complete a task in 30 days. Farjan leaves after 20 days and Kashif alone completes it in another 25 days. How many days does Farjan alone take to complete the entire task?
A. 50
B. 75
C. 60
D. 45 - P can finish a work in 18 days. Q can finish the same work in 15 days. Q worked for 10 days and left the job. how many days does P alone need to finish the remaining work?
A. 8
B. 6
C. 4
D. 2 - P can lay railway track between two stations in 16 days. Q can do the same job in 12 days. With the help of R, they completes the job in 4 days. How much days does it take for R alone to complete the work?
A. 9(3/5) days
B. 9(1/5) days
C. 9(2/5) days
D. 10 days - C takes 6 days to complete half of a work and D takes 5 days to complete 1/3rd of the same work. They take turns to complete the task. If C works for the first 4 days, in how many days will D complete the rest of the work without the help of C?
A. 10 days
B. 12 days
C. 8 days
D. 9 days - A and B can finish a work 30 days if they work together. They worked together for 20 days and then B left. A finished the remaining work in another 20 days. In how many days A alone can finish the work?
A. 70
B. 50
C. 40
D. 60