A. 48 days
B. 24 days
C. 40 days
D. 36 days
No. of days is
directly proportional to the length of the wall and
inversely proportional to the number of men No. of days = (1200/500)*(15/30)*30 = 36 days
Related Mcqs:
- If 3 men or 4 women can construct a wall in 43 days, then the number of days that 7 men and 5 women take to construct it is :
A. 12 days
B. 14 days
C. 16 days
D. 18 days - P and Q can do a work in 30 days. Q and R can do the same work in 24 days and R and P in 20 days. They started the work together, but Q and R left after 10 days. How many days more will P take to finish the work?
A. 10
B. 8
C. 18
D. 19 - 10 men can complete a work in 7 days. But 10 women need 14 days to complete the same work. How many days will 5 men and 10 women need to complete the work?
A. 7
B. 5
C. 6
D. 4 - 3 men and 7 women can complete a work in 10 days . But 4 men and 6 women need 8 days to complete the same work . In how many days will 10 women complete the same work?
A. 50
B. 30
C. 40
D. 13 - 6 men and 8 women can complete a work in 10 days. 26 men and 48 women can finish the same work in 2 days. 15 men and 20 women can do the same work in_______days.
A. 4 days
B. 6 days
C. 2 days
D. 8 days - In a camp sufficient food was provided to 500 men to last for 10 days. But after 5 days 200 more men joined. How long the food will last for after joining the 2000 new men?
A. 3
B. 8
C. 5
D. 1 - A and B can finish a piece of work in 20 days .B and C in 30 days and C and A in 40 days. In how many days will A alone finish the job?
A. 48
B. 34(2/7)
C. 44
D. 45 - A and B can do a piece of work in 21 and 24 days respectively.They start the work together and after some days, A leaves and B completes the rest of the task in 9 days. After how many days did A leave?
A. 5
B. 6
C. 7
D. 8 - P and Q need 8 days to complete a work. Q and R need 12 days to complete the same work. But P, Q and R together can finish it in 6 days. How many days will be needed if P and R together do it?
A. 7
B. 8
C. 9
D. 10 - P can do a work in 24 days. Q can do the same work in 9 days and R can do the same in 12 days. Q and R start the work and leave after 3 days. P finishes the remaining work in_________days.
A. 10
B. 9
C. 11
D. 12