A. longitudinal gradient
B. two times the longitudinal gradient
C. three times the longitudinal gradient
D. half the longitudinal gradient
Related Mcqs:
- Camber in the road is provided for_______________?
A. effective drainage
B. counteracting the centrifugal force
C. having proper sight distance
D. none of the above - When the bituminous surfacing is done on already existing black top road or over existing cement concrete road, the type of treatment to be given is________________?
A. seal coat
B. tack coat
C. prime coat
D. spray of emulsion - The shape of the camber, best suited for cement concrete pavements, is_______________?
A. straight line
B. parabolic
C. elliptical
D. combination of straight and parabolic - For water bound macadam roads in localities of heavy rainfall, the recommended value of camber is_______________?
A. 1 in 30
B. 1 in 36
C. 1 in 48
D. 1 in 60 - The camber of shoulders in water bound macadam roads is________________?
A. equal to the cross slope of pavement
B. less than the cross slope of pavement
C. greater than the cross slope of pavement
D. zero - The camber for hill roads in case of bituminous surfacing is adopted as________________?
A. 2%
B. 2.5%
C. 3%
D. 4% - On a single lane road with two way traffic, the minimum stopping sight distance is equal to______________?
A. stopping distance
B. two times the stopping distance
C. half the stopping distance
D. three times the stopping distance - The shoulder provided along the road edge should be_______________?
A. rougher than the traffic lanes
B. smoother than the traffic lanes
C. of same colour as that of the pavement
D. of very low load bearing capacity - The ductility value of bitumen for suitability in road construction should not be less than____________?
A. 30 cm
B. 40 cm
C. 50 cm
D. 60 cm - The aggregates required for one kilometer length of water bound macadam road per meter width and for 10 mm thickness is________________?
A. 8 cubic meter
B. 10 cubic meter
C. 12 cubic meter
D. 15 cubic meter