A. At the end of reinforcing bar, not less than 25 mm or twice the diameter of the bar
B. In thin slabs, 12 mm minimum or diameter of the bar whichever is more
C. For reinforcing longitudinal bar in a beam 25 mm minimum or diameter of the largest bar which is more
D. All the above
Related Mcqs:
- For 100 sq. m cement concrete (1 : 2: 4) 4 cm thick floor, the quantity of cement required, is_______________?
A. 0.90 m3
B. 0.94 m3
C. 0.98 m3
D. 1.00 m3 - For 12 mm thick cement plastering 1 : 6 on 100 sq.m new brick work, the quantity of cement required, is___________________?
A. 0.200 m3
B. 0.247 m3
C. 0.274 m3
D. 0.295 m3 - A cement concrete road is 1000 m long, 8 m wide and 15 cm thick over the sub-base of 10 cm thick gravel. The box cutting in road crust is__________________?
A. 500 m3
B. 1000 m 3
C. 1500 m3
D. 2000 m3 - The expected out turn of cement concrete 1 : 2 : 4 per mason per day is_________________?
A. 1.5 m 3
B. 2.5 m3
C. 3.5 m3
D. 5.0 m3 - The expected out turn of 2.5 cm cement concrete floor per mansion per day__________________?
A. 2.5 sqm
B. 5.0 sqm
C. 7.5 sqm
D. 10 sqm - While estimating the qualities for the construction of a building, the correct metric unit is________________?
A. Metre for length
B. Cubic metre for area
C. Square metres for volume
D. Litre for capacity - Pick up the correct statement regarding the centre line method of estimating a building?
A. Product of the centre line of the walls and area of cross-section of any item, gives total quantity of the item
B. The centre line is worked out separately for different sections of walls of a building
C. The centre line length is reduced by half the layer of main wall joining the partition wall
D. All the above - The expected out turn of 12 mm plastering with cement mortar is_______________?
A. 2.5 sq m
B. 4.0 sq m
C. 6.0 sq m
D. 8.0 sq m - The expected out turn of brick work in cement mortar in foundation and plinth per mason per day, is ________________?
A. 1.00 m3
B. 1.25 m3
C. 1.50 m3
D. 1.75 m3 - The concrete work for the following part of the building of specified thickness is measured in square metres_______________?
A. Root slabs
B. Floors
C. Wall panels
D. All the above